Granite Rebuilding Three Segments of I-85
Contractor working on three projects
totaling $190 million
By Debra Wood
As the low bidder on three North Carolina Department of Transportation
contracts, Granite Construction of Watsonville, Calif., entered
the state for the first time five years ago and has been busy
reconstructing and widening 7 mi. of Interstate 85 through
the city of Durham.
"These are three major, complex, urban interstate jobs,"
said Bill McGowan, project manager with Granite. "They
have all of the exciting and challenging features of an urban
interstate."
The existing four-lane highway was designed during the 1950s
and now handles 85,000 vehicles daily. Volume will reach 138,000
vehicles per day in 2025.
"We needed more capacity to handle the traffic volume
coming through the Durham corridor," said Aaron Earwood,
resident engineer with NCDOT. "All of the interchanges
were outdated with excessive access points. We have redesigned
and reconfigured all of the interchanges to limit those and
make them safer."
The new road will have at least four lanes in each direction,
plus additional auxiliary lanes between interchanges. There
also are collector-distributor lanes to allow traffic to enter,
merge and exit more safely. The project includes 20 new bridges.
NCDOT considered the size and complexity of the entire project
too large to bid as a single contract and divided it into
three segments. It awarded each to the low bidder.
"Fortunately the same contractor won all three projects,
which has helped with continuity and tying in the jobs together,"
Earwood said. "[Granite] won the bid. Once you have the
first project, you have an advantage bidding on the other
two projects."
Granite began work on the first, $50 million interchange
improvement project in August 1999. The job entails adding
access points between I-85 and U.S. Highway 70. U.S. 70 will
gain one lane in each direction. Cars will be able to exit
westbound U.S. 70 to northbound I-85.
And from a 2,600-ft. flyover, they will be able to access
eastbound U.S. 70 from southbound I-85. Westbound U.S. 70
will merge in a slow lane on southbound I-85. This interchange
work should finish in spring 2005.
The second, $73 million contract began in April 2001. It
includes construction of eight steel-girder bridges, which
will be wider, longer and higher than the existing structures,
and reconstruction of two major intersections. The first existing
intersection had 11 exits and entrances.
"We're simplifying it, adding collector-distributor
roads and reducing 11 ramps to four ramps," McGowan said.
The second intersection is near a mall. The new design has
a separate exit for the shopping center and the neighboring
surface road.
Work started on the third, $68 million contract in July 2003.
Granite will replace three permanent bridges. Crews will build
a flyover to replace the current fast-lane exit from southbound
I-85 to U.S. Highway 15/501 with a slow-lane off-ramp.
Along most of the corridor, Granite will add thousands of
square feet of brick noise-reduction walls. There are no noise-mediation
walls on the first job.
The two widening and bridge-replacement projects - the second
and third projects - should wrap up in 2006. The I-85 projects
are behind schedule due to unexpected aerial utility delays.
"The schedule was extremely aggressive on this high-profile
project," McGowan said. "It is considered some of
the most complex interstate project going on [in the state]."
Yates Construction Co. of Stokesdale, N.C., is handling underground
utility relocations. Some of the 200,000 lin. ft. of water
lines the company moved dated back more than 100 years.
The project included 2 million cu. yds. of earth moving.
Crews have built retaining walls and mechanically stabilized
earth walls.
A stream runs along the southbound side of the highway through
most of the project. After the utilities were moved, Mountain
Creek Contractors LLC of Claremont, N.C., added box culverts
and diverted the stream. The box culverts run under the ramps
and interstate. Some tie into existing culverts.
"There is a lot of intricate blasting," McGowan
said. All together, crews blasted more than 200,000 cu. yds.
of rock located about 50 ft. from homes.
"You cannot just load them up full of dynamite and,
boom, blow it up," he added. "You have to drill
close patterns and keep the amount of charge to a minimum
so you don't create a lot of vibration that causes the houses
to fall down."
All three projects entail significant detour work. Granite
is using six temporary, prefabricated bridges from Acrow Corp.
of Carlstadt, N.J., and developed a complex staging plan.
A narrow right-of-way left little room for shifting traffic
to the outside.
"We committed to maintain two lanes in each direction
except at night, so they've had to do extensive detour and
traffic phasing," Earwood said.
On all of the sections, Granite builds a detour to the outside
of the existing lanes. Crews subsequently remove the old lanes
and construct the median portion of the highway.
"Then we take the traffic onto the median, take it off
the outside detours and finish the outside of the new road,"
McGowan said. "We essentially have to build the interstate
twice."
Nested in the third contract is a design-build component
for off-site detour improvements through the city of Durham.
Granite worked with Greenhorn & O'Mara of Raleigh, N.C.,
a civil engineering consulting firm, to increase capacity
during the traffic rerouting.
Granite added a center turn lane to one of the roads and
enhanced drainage, grading and signalization at the intersections.
The upgrades will remain after the interstate work finishes.
"The design-build is something new we have tried,"
Earwood said. "It went really well."
As of July, the first project was 85 percent complete; the
second, 65 percent complete; and the third project, 30 percent
complete. Asphalt paving is on going on all three segments,
and Portland cement concrete pavement work has begun on the
first two jobs.
Granite is using the same crews and subcontractors on all
three jobs. It has about 150 workers onsite and is self-performing
the grading and structures. About 50 to 100 employees of subcontractors
are also working on the project during the peak summer construction
season.
"We're building a good crew of professional workers
in Durham," McGowan said. "And we're establishing
a professional and good relationship with the North Carolina
Department of Transportation."