|
One Tough Job
Hubbard Construction's I-95 Widening
Project in Delray Beach Had Its Problems
By Scott Judy
Orlando-based Hubbard Construction Co. was able to complete
a complex, problem-filled Interstate 95 widening project in
Palm Beach County on schedule this summer and to the satisfaction
of the owner - all despite the contract value growing by more
than 25 percent.
Originally awarded at $49 million, the Florida Department
of Transportation design-build project escalated to $62 million
as redesigns and unexpected site conditions caused additional
work.
By finishing slightly ahead of the Aug. 17 completion date
- the original deadline for the 1,385-calendar day job, Hubbard
expected to earn considerable bonus funds, and had already
received over $1 million for finishing up early on two major
interchanges for the city of Delray Beach.
"The construction is good, high-quality craftsmanship,"
said Scott Burrie, construction project manager for FDOT.
"(There is) no problem with Hubbard as far as the overall
construction."
Bill Capehart, vice president and division manager for Hubbard,
summed up his company's feelings at the end of the job when
he said, "It was a tough job."
Thomas O. Craft, Hubbard's construction manager for this
project, assisted Capehart. Other key Hubbard staff included:
Jim Cardaman, project manager; Mike Dempsey, project superintendent;
and Gary Montgomery, bridge superintendent.
The Project
Bid in June 2000, the project consisted of widening approximately
3.86 mi. of I-95 from six to 10 lanes, the reconstruction
of eight ramps, demolition and rebuilding of 10 bridges at
five different locations, plus major rebuilds of Linton Boulevard
and Atlantic Avenue at those respective interstate interchanges.
The I-95 project is bound by the L-30 canal on the north end
and Linton Boulevard on the south.
It was definitely a big job. Project quantities included
534,000 cu. yds. of excavation, approximately 275,000 sq.
ft. of temporary or permanent mechanically stabilized earth
wall, over 310,000 tons of limerock base (including temporary)
and about 170,000 tons of asphalt (including temporary).
The bridge work required about 200 prestressed concrete beams,
ranging from 80 to 131 lin. ft. each, and nearly 400 concrete
piles. Storm drainage necessitated 20,200 lin. ft. of pipe
and 185 inlets/manholes.
Despite the huge materials quantities, a bigger issue was
the project's plan for maintenance of traffic, or MOT, the
contractor's plan to work with, in and around the estimated
165,000 vehicles traveling through the project daily - many
of them at high speeds. The MOT plan includes the contractor's
project staging, use of barrier wall or other devices, and
other efforts to keep the stretch of roadway open to traffic.
"The maintenance of traffic is probably the most important
thing on these jobs," Burrie said. "Our typical
speeds are running between 80 and 85 mph in a posted 55 mph
work zone. We've got narrowed lanes in all of our phases of
construction. So we've got lots of motorists doing white-knuckle
driving trying to go through the construction zone at 60 or
55 and people passing on the left and right at 75, 80 and
85."
Winston Lucky, senior project engineer with designer HNTB,
called this job's MOT "the biggest challenge," not
only because of the fast and furious traffic, but because
of design changes and unexpected site hurdles.
The Problems
The original idea was to build the project in thirds, starting
from the north end and heading south in a slow-but-steady
and orderly fashion. Delays encountered driving sheet pile
necessitated a change in plans.
"We had a lot of problems installing the sheet pile
that was needed to shore up the existing roadway in order
to build the new road right next to it," FDOT's Burrie
said. Engineered fill used to build the road approximately
30 years ago proved difficult to pass through.
"We couldn't drive the sheet pile," Burrie added.
Hubbard officials explored and thought it may have been a
case of differing site conditions. However, Burrie said, "Upon
coring the job we found the site conditions were exactly as
presented in the plans, but it still didn't reveal the problem."
(The identical problem would eventually be encountered at
every location - mostly at every corner of a bridge - where
engineered fill was found.)
After several months of analysis, the team decided on the
ultimate solution of predrilling or soil disturbance where
the sheet pile was to be driven.
"We did test piles in accordance with all DOT standards,"
Lucky said. "But all they could do was predrill it to
help with the penetration." Though this method added
considerable cost, it worked.
Burrie said that prior to this solution, "We were making
a lot of noise and things were delayed months and months and
months."
To partly address the delay problems, the team introduced
a new MOT scenario that, instead of thirds, split the job
in half. By committing to this new traffic switch, Hubbard
agreed to not ask for extensions due to the pile-driving problems.
This enabled the contractor to work on more areas at once,
such as multiple bridges, so that instead of being built one
after the other, they were constructed concurrently.
Hubbard kept the job on track as much as it could, Burrie
said.
Ramp reconstruction would stymie the design-builders as well
and eventually add further cost to the project. Initial cross-sections
of the ramp areas were problematic. If built as designed,
the ramps would not be able to be kept open during construction.
That consequently changed the engineering of all eight ramps
on the project - and caused a further escalation in price.
By making these changes, the construction team was able to
keep several ramps open during reconstruction, but ultimately
some had to be shut down.
"Maintaining traffic just became insanity," Burrie
said. "It was nightmarish."
Further costs were incurred because additional signing was
required to route traffic.
"The MOT on this job was so complex, if you change one
portion of it, it's like a ripple effect," said HNTB's
Lucky, adding that side-street detours were especially problematic.
The Progress
Hubbard's Capehart agreed that the required phasing was the
most difficult part of the job. The contractor first expanded
the road to the outside with temporary lanes and then started
working in the median. Here, safety was the key factor.
"You've got to be safe," Capehart said. "Accessing
the median was a tremendous concern of ours." Getting
trucks in and out of the median as cars whizzed by, for example,
was one item the contractor had to deal with. Another change
to the MOT to enhance safety was made here by expanding the
shoulder to a full breakdown width.
Even by expanding the roadway to the outside, working in
the median "was a tight fit," Capehart said.
The contractor self-performed the vast majority of the project,
with company subsidiary East Coast Paving handling the asphalt
work. Johnson-Davis of Lantana installed the storm-drainage
pipe.
The new road was built with 11 in. of limerock on stabilized
subgrade, with 6 in. of asphalt and a 1-in. friction course.
East Coast Paving was placing the final lift of friction course
in early summer.
Burrie said that going into the final stretch, he was becoming
more pleased with HNTB's efforts, and with Lucky in particular.
"In the past year, we've stabilized with a single designer
(Lucky), and he's come to work very closely with the team,"
Burrie added. "We've had good response from HNTB in the
past year. The problem was in the first year-and-a-half, when
we had all of these monumental problems.
"In the beginning it was a little touch-and-go and I
really wasn't happy, but here in the past year they've come
around."
As for the efforts of Hubbard, and of the job overall, Burrie
said: "We had monumental problems and the contractor
was handicapped by us not having designs for them when needed
when we encountered these problems. But we've got a good job
coming to completion."
Project Team:
Owner: Florida Department
of Transportation
General Contractor: Hubbard
Construction Co., Orlando
Designer: HNTB, Miami
Construction Engineering and Inspection
Firm: Greenhorne & O'Mara, West Palm Beach
Asphalt Contractor: East
Coast Paving, a subsidiary of Hubbard Construction
Utility Contractor: Johnson-Davis, Lantana
|