|
Schooled in Design-Build
Design-Build Teams Wrap Up Two
South Florida High Schools
By Debra Wood
School boards in Palm Beach and Broward counties hired James
B. Pirtle Construction Co. of Davie, Fla., to design and build
their recent high school projects and are pleased that the
jobs will wrap up ahead of schedule.
"Design-build is the best delivery method we have,"
said Greg Boardman, a project manager with Broward County
Public Schools. "It's definitely much faster. And it
has terrific advantages as far as change-order percentages.
They are very low, because the architect is directly reporting
to the contractor."
Broward County Public Schools contracted with Pirtle to design
and build Coral Glades High School in Coral Springs and Palm
Beach County School District brought in the contractor for
its West Boca Raton Community High School.
Coral Glades
Broward awarded Pirtle the $27 million contract to design
and build Coral Glades High School in Coral Springs in November
2002. Zyscovich Inc. of Miami designed the two-story, courtyard-style
school.
"I like the design-build arena because it affords the
advantage of direct or open communication between the architect
and contractor," said Bill Oakman, Pirtle project manager
for the high school.
Pirtle had completed two prior design-build schools with
Zyscovich, and the companies had worked on several other projects
together. Both firms have extensive portfolios of completed
schools. Zyscovich Vice President Jose Murguido said that
experience helped secure the Coral Glades contract.
"The Broward County School Board has a multitiered review
process for design-build submissions," he added. "They
evaluate not only the design and price, but also the strength
of the team, its longevity together, its past performance
and its experience with K-12 facilities.
"One of the key factors of a successful design-build
process is a working relationship between the builder and
architect. You do not want to go through relationship building
as you are designing a building in an accelerated design process."
A delay in obtaining the land pushed construction back by
a couple of months. The city of Coral Springs owned the site
and entered into an agreement with the school district in
which the school could occupy 20 acres of the city's Sportsplex
at Coral Springs. Those acres had been leased to a golf practice
facility.
Under the agreement, athletic fields would be placed in the
sports complex and shared by both the school and public. Sportsplex
participants would be allowed to park at the school.
Even though breaking the lease with the golf course operator
delayed groundbreaking, the school district did not extend
the completion deadline because it needed the school to open
in August. Pirtle had recently completed a similar structure,
and while Coral Glades had some modifications, the team felt
confident it could finish it in time.
Once on site, Pirtle needed to remove and haul away 100,000
cu. yds. of muck and replace it with 50,000 cu. yds. of good
soil. Coral Springs is noted for its cap rock, and Pirtle
crews found much rock at the site.
"We could watch these huge machines work more like a
chipper than a digger," said Paul Carty, Pirtle vice
president and the project executive. "You'd see sparks
flying off the rock. It was a very slow process."
Pirtle also added utilities and building pads for an auditorium
and a future classroom building. About 1,600 students will
attend the 220,000-sq.-ft. campus, which includes four tilt-wall
buildings.
The city of Coral Springs awarded Pirtle a separate $7.6
million design-build contract to widen the access road and
complete the school's track, tennis and basketball courts,
concession stands and other athletic amenities.
Carty served as project executive for both jobs. Each has
a separate project manager. It completed the city work in
the spring and expected to wrap up minor finishing work before
opening day on Aug. 16.
"Our proudest thing is being able to deliver the school
so the students are able to start in August," Carty said.
"We made a commitment to them up front. Although we had
a two-month delay getting going, we stuck with that commitment."
West Boca Raton
Pirtle completed the $42.5 million West Boca Raton Community
High School for the Palm Beach County School District more
than four months ahead of schedule. On this project, it paired
with Song & Associates Inc. of West Palm Beach.
"Song & Associates had extensive experience and
relationships with the school district of Palm Beach County,
and they also did a lot of preliminary work to develop a plan
to respond to this request for proposals," said Pirtle
Vice President Mike Geary.
Rodney Crockett, project manager for Song, said the project
went well, considering the unusually short timeframe. The
team received the contract in July 2002, and the 330,000-sq.-ft.,
tilt-wall project broke ground in September of that year.
It will provide space for 1,917 students.
This school has a two-story, 12-building, courtyard-style
campus. Unlike the Broward County project, Song developed
a completely new design for the unique triangularly shaped
West Boca site.
"We, as the design-builder, and our partner Song had
to be creative to come up with a site solution that would
maximize the use of the site while maintaining school operations
that would be practical once the school opened," Geary
said.
Before proceeding, Song met with nearby property owners,
seeking their suggestions. Several large developments are
located in the surrounding area.
"They are pretty sensitive about what goes in their
community," Crockett said. "The school fits in the
neighborhood and has a nice upscale look, with a curved, covered
entry with columns and palm trees."
Tom Johns, director of program management for Palm Beach
County schools, said the land acquisition was an issue, but
the school district ultimately reached an agreement with the
county to purchase low-lying land adjacent to a future park.
Crews moved 250,000 cu. yds. of dirt to fill in the school
site.
"We were able to take fill [and create] a lake at the
park," Johns said. "It turned out to be a good project,
both as a design-build and in our dealing with the county."
The Palm Beach district uses a design-build approach for
about 10 percent of its projects. The Pirtle bid came in $4
million less than the next lowest bidder on West Boca.
"The price of a design-build project has a lot to do
with the design," Carty said. "We had a very efficient
design, and that was the single biggest difference in the
pricing."
Design-build projects represent about 40 percent of Pirtle's
contracts. "One advantage we feel as design-builders
is that we have a direct relationship with the architect,"
Geary said. "As a result, we are able to persuade them
to be more responsive to the needs of the construction component."
As with the Broward job, construction proceeded uneventfully
at West Boca.
USEFUL SOURCES:
Palm Beach County School District
- West Boca Raton Community High School http://165.161.3.47/mpr/status_report.cfm?proj_id=40
Broward County Public Schools - Coral
Glades High School
http://www.browardschools.com/district/archive/archive52.htm
|