|
Design-Build-Operate at Camp Creek
Western Summit, Parsons and American
Water Combine for Georgia's First D-B-O Contract
By Scott Judy
To expand its Camp Creek Water Reclamation Facility, the
Fulton County, Ga., Department of Public Works hired three
national firms with extensive expertise in the field of water
supply projects to design, build and operate this revitalized
plant.
The $132 million design-build-operate contract - the first
of its type in Georgia, and, at the time, Fulton County's
largest-ever contract - expanded the existing plant's capacity
from 13 million gallons per day to 24 million and provided
for 15 years of contracted operation.
To date, that leap into the D-B-O procurement method is paying
off, as Western Summit Constructors of Denver; Pasadena, Calif.-based
Parsons; and American Water of Marlton, N.J., are set to complete
the facility on time in January and on budget.
"That shows this D-B-O process works, and works well,"
said Tim Equels, assistant director for the Fulton County
Department of Public Works.
Mike Powers, Southeast division manager for Western Summit,
said proving the merits of D-B-O was an important aspect of
the project.
"We've proven that this type of procurement process
does work, and we've proven it with a major municipality here
in the Southeast," he said. "Hopefully that will
help other municipalities fall in line."
The Project
Fulton County selected the design-build-operate team of American
Water/Western Summit/Parsons in November 2001 and came to
terms on an operational contract with American Water in March
2002. The company took over operations of the plant the next
month, and the county issued the design-build Notice to Proceed
on June 24.
The design-build portion of the contract equals roughly $85.3
million, with approximately $3.9 million of that a result
of an emergency project change order to add two "package
plants" on a temporary basis. The remaining $47 million
covers American Water's agreement to operate and maintain
the facility for 15 years.
The project included re-rating the existing facility to an
8 MGD capacity at enhanced effluent standards and then adding
a new 16 MGD plant. This construction plan simplified construction
sequencing to provide continuous facility operation.
"Essentially you can either increase the tankage and
(other equipment) in there, or you can decrease the flow and
treat less and get better performance," said Dan Eckdahl,
site manager for Western Summit. "We opted to do treat
less through that existing plant and add a 16 MGD treatment
process."
Additionally, the project included construction of a new
headworks facility, three new primary clarifiers, three new
secondary clarifiers, three biological reactors, an ultraviolet
disinfection system, a new filtration system, 4,000 ft. of
60-in. outfall pipeline and biosolids handling facilities.
Modifications to existing influent sewers and force mains,
primary clarifiers, secondary clarifiers and conversion of
existing aeration basins also were included.
Other notable project quantities included 347,000 cu. yds.
of site/structure excavation, 347,000 cu. yds. of site/structure
fill; 29,000 cu. yds of structural concrete; 6,800 lin. ft.
of 15- to 72-in. reinforced concrete pipe; 21,000 lin. ft.
of 4- to 54-in. ductile iron pipe; 4,600 lin. ft. of small-diameter
PVC piping; and 8,600 lin. ft. of small-diameter double-containment
PVC chemical piping. Western Summit's electrical contractor,
Excel Electrical Technologies, will have installed 31 mi.
of conduit and 152 mi. of conductor wire.
Western Summit self-performed approximately 70 percent of
the total contract, but it subcontracted a $5.3 million turnkey
contract to minority firm Thacker Southern to build an onsite
operations/maintenance facility.
Equels, the Fulton County official, said the Camp Creek project
was all about risk management.
"It goes to prove why this design-build-operate (method)
was successful," he said. "It transferred a lot
of risk over to the contractor team.
"The risk was on them, rather than the county, so we
didn't have to worry about all of the little details. And
they didn't address (project problems) with us because they
were guaranteeing the project."
Timing
Though the plant was being pushed to capacity due to area
growth, the project had been languishing within the public
works department for several years, Equels said.
"So this (the D-B-O) was a good opportunity to get the
project started and to fast-track the acquisition," he
added.
The project had been scheduled to commence in 2001, but the
county awarded the contract about a year later than expected,
and Western Summit/Parsons received its Notice to Proceed
in June 2002, exactly 12 months later than planned. To expedite
the project as much as possible, Western Summit opted to jump
the gun a bit.
"We kind of went out on a limb," Eckdahl said.
"In January 2002, we were certain enough that we were
getting the job that we pushed Parsons to start designing.
So when June 24 came, the day we got our notice to proceed,
we had phase one 100 percent designed, and we were able to
break ground with that construction immediately."
An initial milestone to have the tertiary treatment and UV
disinfection portion of the new plant operational by early
2003 forced a change from the contractor's original plans.
The milestone was mandated by changing requirements of the
Georgia Environmental Protection Division.
"We really didn't have a phased approach at proposal
time because we thought we could design everything in six
months and then start construction," Eckdahl said. "From
June 2001 we would have had six months to design and between
six and nine months to construct the first phase."
By starting design early, the design-build team was able
to complete phase one within nine months of its contract start
date.
Design on phase two - the new plant - was completed in February
2003, and the team received Notice to Proceed in March.
Project Curves
At about the same time, the Southeast was experiencing historic
rainfall amounts, and Fulton County was experiencing a nearly
record homebuilding pace. For those reasons, the 13 MGD plant
was experiencing overcapacity water flow and was about to
violate its permit. The Georgia Environmental Protection Division
demanded the situation be corrected "in short order,"
Eckdahl said.
After brainstorming various options, the DBO team and Fulton
County agreed to relocate and temporarily use two existing
"package plants" - previously out of commission
for about 10 years - from another county plant. Because the
proposed location of the package plants at Camp Creek was
on top of an abandoned sludge lagoon - which was to be cleaned
out and capped off with dirt by a third-party contractor -
this delayed work from starting by about four months.
The change order had called for an April 2003 start for this
work, and a December completion date. And though the contractor
wasn't able to start until late August, it still made the
Dec. 15, date.
That was important because with the addition of the package
plants, the design-builders were able to get the plant rated
to 19 MGD, and get the county back within the terms of its
permit.
Notably, the heavy rain - and its minimal impact on the contractor,
and the county - was another item Equels cited as indicative
of the benefits of D-B-O.
"When you consider all of the obstacles they've had
to go through, such as the worst rainfall in state recorded
history, and all of the things that could have been claims
for delay and change orders - none of that ever occurred,"
Equels said.
Indeed, to date, the contractor had experienced approximately
30 days of rain beyond what it had anticipated going into
the project, with no adverse impact, and was on schedule.
"We're getting an excellent product at a great price,
with a good guarantee," Equels said. "So we're happy."
USEFUL SOURCES:
http://www.westernsummit.com/portfolio/featured/campcreek.php
PROJECT TEAM:
Owner: Fulton County Department
of Public Works
Contractor: Western Summit
Constructors, Denver
Engineer: Parsons, Pasadena,
Calif.
Operator: American Water,
Marlton, N.J.
|