|
Building the Wilmington Bypass
GLF Construction Corp. is Erecting the $85.5 Million River Span
By Scott Judy
GLF Construction Corp. of Miami and its team of subcontractors
are finally heading into the final stretch of its $85.5 million
Wilmington Bypass project over the Northeast Cape Fear River
in North Carolina.
It has been a long time coming. The project was slow going
because it required building an extensive drilled-shaft foundation
system for the structure located in the middle of a sensitive
wetlands area.
Work began Jan. 15, 2001, and the target for completion
is now June. Though the drilled-shaft work has taken twice
as long as originally anticipated, Ed Thornton, contracts
manager for GLF, said, "We're about where we thought
we would be."
Despite the obstacles, officials with the North Carolina
Department of Transportation are mostly positive."We're
a little behind schedule, but overall I think everything's
gone real well," said O.T. Anderson, NCDOT resident engineer.
"GLF's done a good job. The subs have done a real good
job. It's just a matter of getting it done."
NCDOT's positive opinion can be attributed to the project's
minimal environmental impact.
"Environmental was the major concern," Anderson
said. "Getting in the drilled shafts, and making sure
we didn't have problems with leakage of the slurry, has gone
extremely well."
TreviIcos South of Tampa was the subcontractor for the drilled
shafts, which numbered 500.
Project Basics
GLF and its team are constructing approximately 4.25 kilometers
of four-lane divided highway, with the greatest focus on the
2.3-kilometer-long bridge structure spanning the Northeast
Cape Fear River and adjoining wetlands. GLF's Thornton said
the contractor is currently finishing the second half of the
segmental portion of the channel span.
"We have finished the north-side approaches to the channel
span and the north half of the segmental cast-in-place box
girder bridge," he said. "We are currently about
halfway finished with the south approach to the bridge."
GLF is self-performing the structure work and has subbed
out the earthwork and associated roadway construction and
landscaping to Triangle Grading & Paving Co. of Burlington,
N.C.
The bridge utilizes a rather unique combination of two different
construction methods. Approach bridges leading up to the main
river span are being built with precast/prestressed bulb-tee
girders and cast-in-place concrete decks. The 146-meter-long
main span is then being built with cast-in-place cantilevered
box girders. This section will have a vertical clearance of
roughly 24 meters over the Northeast Cape Fear River.
T.Y. Lin International's Alexandria, Va., office handled
the engineering of the river-span section. Reggie Holt, senior
project engineer, said the cast-in-place box method won out
over cable-stayed and arch alternatives.
"The primary force for the structure as a whole was
vessel impact, which forced the piers to be outside the confines
of the Northeast Cape Fear River," Holt said. "We
were dictated span lengths in the realm of 500 ft., so once
that decision was made, we were fairly limited on the type
of structure that could make that span.
"We looked at (initial) costs, life-cycle costs and
other performance issues. And the preferred alternative turned
out to be the concrete box." Holt added that while the
arch form had the highest initial cost, the cast-in-place
box method beat out the cable-stayed alternative with lower
life-cycle costs.
Precast box construction wasn't possible, either, due to
the bridge's variable-depth box design and also the length
of the span. Thornton said cast-in-place segmentals generally
can achieve longer spans than precast segmentals.
Cast-in-place is "more difficult" than precast
segmental erection and "a little slower," Thornton
said. "With precast you may have the advantage of having
your superstructure cast out by the time you get your substructure
built."
Thornton explained that the balanced cantilever method of
segment erection calls for casting and post-tensioning a segment,
then launching the formwork system out from there, installing
post-tensioning ducts and reinforcing steel for the new segment,
and then pouring the concrete.
The segments are massive, measuring about 29 meters wide
and featuring an interior height of about 35 ft.
GLF is also self-performing the deck work, which it expects
to complete by March.
Drilled Shafts
Both bridge structures rest upon drilled shafts ranging
from 1,220 mm to 2,439 mm in diameter installed to an average
depth of approximately 24 meters. The shafts are drilled within
permanent steel casings for the top 40-50 ft. of excavation.
Below that, the drill rig excavates down to a depth of about
80 ft. through organic material such as peat.
Bud Khouri, vice president and regional manager for TreviIcos
South, said the driving challenge was working in the wetlands
environment. For starters, absolutely no bit of extraneous,
excavated material, or spoils, could be allowed to fall back
into the area surrounding the project.
"It's such an environmentally sensitive area that we
took extra precautions and a lot of extra measures that we
would not have taken had it not been in such an environmentally
sensitive area," he added. "For instance, we made
sure nothing dropped down - no dripping of anything of any
sort, especially slurry, down into the swamps."
Excavation contractors use slurry in their drilling rigs
to maintain an open hole in the area below the casings. Slurries
are generally comprised of bentonite-type clay or polymer.
TreviIcos proposed utilizing a polymer-based slurry that is
more environmentally friendly.
After TreviIcos performed onsite load tests and proved to
NCDOT that a polymer slurry would work just as well, the department
approved the use of polymer. That was an exceptional occurrence;
NCDOT and Khouri said they believe this is the first large
DOT project to use a polymer slurry.
Overall, this part of the project has been difficult. TreviIcos
started its work in August 2001 and now expects to wrap up
by October. "That's the schedule right now," Khouri
said recently, adding that the company was installing five
shafts per week and had about 52 left to install.
Working in the Wetlands
Much of the slow-going can be attributed to the working
environment. Contractors have to be careful how they work,
and access to the site is limited.
To minimize the impact, NCDOT mandated that all construction
be staged from a trestle bridge built over the wetlands. NCDOT's
original plan was to have such a bridge on each side of the
project. Instead, GLF proposed and eventually utilized a trestle
on only one side. The company sought to enhance the trestle's
productivity by incorporating a rail line that would deliver
materials in and out of the job.
The wooden trestle, built on 24-in. pipe piles, has accommodated
as much as seven American 9310 cranes at one time.
"Accessing your materials and personnel along a trestle,
across a marshland, safely and productively and doing this
in an environmentally friendly way - it's just challenging,"
Thornton said.
Still, he said he's pleased with the result of his company's
diligence to the project's environmental issues.
"We've been particularly sensitive to the environment,"
he said. "If you take a walk down that trestle, you'll
see that the area's cleaned up. We take the necessary precautions
and we're sensitive to it."
Project Team:
Owner: North Carolina Department of Transportation
General Contractor: GLF Construction Corp., Miami
Bridge Designer: URS/Greiner and Woodward Clyde
Designer, Main Span: T.Y. Lin International, Alexandria, Va.
Drilled-Shaft Contractor: TreviIcos South, Tampa
Roadway and Landscaping Contractor: Triangle Grading &
Paving Co., Burlington, N.C.
|