|
Palm Beach Co.'s System 3
$36.5 million project one of biggest
of its type in Florida
By Debra Wood
To enhance the quantity and quality of available drinking
water, Palm Beach County Water Utilities Department has contracted
with Poole & Kent Co. of Miami to construct a $36.5 million
facility at its System 3 Water Treatment Plant west of Delray
Beach.
The new structures will replace existing water-treatment
facilities and enable the county to increase production to
30 million gallons of drinking water per day. The plant will
use nanofiltration technology, which uses a partially permeable
membrane to remove organic compounds and soften the water.
"Because it's an expansion of an existing facility,
we're constructing the plant in phases while the existing
plant continues to run," said Larry Johnson, project
manager for the county. "We are going to be converting
the existing membrane-softening plant to house our pumping
equipment. We will be demolishing the interior of the existing
process plant and installing the pumping systems for the new
plant in that existing building."
Poole & Kent began construction in June 2002, with final
completion of the four-phase project scheduled for June 2005.
The company is part of the EMCOR Group of Norwalk, Conn.,
as is the electrical subcontractor Dynalectric of Miami.
Camp Dresser & McKee Engineers of Maitland, Fla., is
the engineer of record. About 60 people are working onsite.
The project includes six cast-in-place concrete and block
structures, 10 new membrane softening units, upgrades on the
chemical systems, two new 2,000-kw diesel generators for emergency
backup power supply, a second clearwell, a transfer pump station
and a 5-million-gallon storage tank.
With the water table about 2 ft. below grade and the yard
piping, duct banks and foundation under water, Poole &
Kent installed an extensive dewatering system. Company officials
had considered open pumping or well pointing but decided to
use a deep-well system that Mike Brown, Poole & Kent's
project manager, had used on a previous job in central Florida.
Crews strategically placed 15 40-ft.-deep, 6-in.-diameter
wells connected to 5-hp pumps. The combination of wells drew
the water table down 10 ft. This is the first time Poole &
Kent has employed the deep-well technique in South Florida
and is pleased with the results.
During the first phase, crews built the nanofiltration membranes
building and installed pipes to the existing pumps, which
will power the plant on a temporary basis.
Poole & Kent built the currently operating membrane plant
in the 1990s. On the current project, during the second phase
of construction, the contractor will demolish the interior
and change its function to a pump building.
"We were literally working inside the existing building,
and the contract design called for us to go in the building
and drive sheet piling, remove all the existing slabs in certain
areas, redo the piping and pour new slabs," said Pat
Carr, executive vice president for Poole & Kent. "It
was very unusual."
Brown sought to expedite work in the first phase to give
the company more time to complete the more intricate second
phase. He consulted with the structural engineers about ways
to protect the existing structure while starting to demolish
portions of the plant before the water supply is switched
to the new nanofiltration units.
His concerns included the affect of vibration on the existing
filtration units, the danger of undermining the foundation
and risks associated with moving equipment around in the enclosed
plant.
"We did some revision [on the plans]," Brown added.
"For instance, the pipes were spread apart and deep.
We moved the pipes up to a higher elevation and compressed
them [the pipes] a little bit, so they can stay farther away
from the building foundation."
The plan also minimized the need for driving sheet piles.
The company installed half of the underground 42-in. and 54-in.
pipe before shutting the plant down in January. Later the
company put in 15 new 200-hp and 400-hp pumps.
Poole & Kent completed eight major tie-ins during regular
working hours, but two additional tie-ins took place during
off-peak water consumption hours.
"The contractor worked well with our operating personnel
in coordinating the shutdowns that were required for installation
of underground piping and being able to do this large project
while still maintaining the operation of the existing plant,"
Johnson said.
Phases three and four involve installing a membrane clean
system and final site work. Carr and Brown consider both later
phases minor components of the job.
Carr said the new membrane plant "will be one of the
biggest in the state."
System 3 Water Treatment Plant Project
Team:
Owner: Palm Beach County Water
Utilities Department, West Palm Beach
General Contractor: Poole &
Kent, Miami
Engineer: Camp Dresser &
McKee Engineers, Maitland, Fla.
Electrical Contractor: Dynalectric,
Miami.
|