|
The Lake Murray Backup Dam
$275 million dam should be complete by year's end
By Debra Wood
As it has for nearly 75 years, the Lake Murray Dam will continue
to serve the people of South Carolina, diverting water from
the Saluda River for energy production and creating a beautiful
recreational lake - even after completion of a new $275 million
backup dam.
"The existing dam will remain as it is and be the primary
dam," said Sam Stockman, project manager with South Carolina
Electric & Gas of Columbia, S.C. "The new dam will
act strictly as a backup."
At one time, Lake Murray Dam was the largest earthen dam
in the world built for power production. Federal Energy Regulatory
Commission earthquake safety criteria forced SCE&G to
construct a backup dam with the ability to withstand a major
earthquake, after learning the current dam was vulnerable
to widescale embankment liquefaction.
"It was determined the existing dam had problems if
we had a seismic event, like a repeat of the Charleston earthquake
of 1886," Stockman said. "This is the reason we
are retrofitting on the downstream side and building another
dam."
That seismic event caused extensive property damage and
killed about 60 people. Although this earthquake occurred
nearly 50 years before Charles F. Richter developed his earthquake
scale, the U.S. Geological Survey estimates the Charleston
quake had a magnitude of 7.3. It remains the most damaging
earthquake to hit the Southeast and represents one of the
East Coast's largest shocks.
Paul C. Rizzo Associates of Pittsburgh, Pa. and Columbia,
S.C., developed the remedial design and is serving as construction
manager on the backup dam. The structure has rock-fill berms
at the base of the existing dam and a 2,300-lin.-ft. center
section built out of 1.3 million cu. yds. of roller-compacted
concrete.
Rizzo's plan called for constructing a portion of the new
structure along the back of the old dam, between that dam
and the utility company's hydroelectric and coal-fired steam
generating plants.
Both plants needed to stay operational during construction.
The steam plant had experienced two short outages in the spring
associated with the project, and the hydro plant had stayed
online except during planned down times to re-route water-supply
lines.
"We went to a lot of effort to put together detailed
drawings," said Jeff Bair, project manager for design
with Rizzo Associates. "The level of detail has really
saved time, and it gave us a good idea of what we would find
when we dug down."
While preparing to bid on the project, Barnard Construction
Co. of Bozeman, Mont., built a scale backup dam as a visual
tool and to figure out sequencing. The company came up with
a plan that shaved 10 months off the schedule.
"Instead of starting in the center, which had a lot
of constraints with the two power plants, we worked the north
and south side at the same time and got that work done early
before the more difficult sections," said Neil VanAmburg,
Barnard's project manager. "We looked at it as a couple
of different projects."
Barnard began constructing the 1.5-mi.-long dam in August
2002. Stockman said the project is on time, with a December
finish for the dam and a spring 2005 completion of all associated
work. About 250 people are working onsite, during two 10-hour
shifts, six to seven days per week.
SCE&G awarded Griffin Dewatering Southeast of Houston
the dewatering system contract prior to letting the construction
work, enabling Griffin to lowering the water table within
the dam for stability and to allow for the foundation excavations
to proceed without water intrusion. Extensive dewatering,
using 1,000 wells, was required to provide safety against
slope instability during construction.
"It is the most challenging job we have ever had,"
said Harry Bagherzadeh, project manager for Griffin. "We
had at the same time eight pumps running both shifts."
Griffin pumped the water to a discharge area that leads
to the Saluda River. During dewatering and excavation, Rizzo
monitored the existing dam so it could observe any movement
and make sure it was reacting as expected.
Before starting the project, SCE&G lowered Lake Murray
from 50,000 acres to 40,000 acres. An independent panel of
experts recommended lowering the lake to increase the margin
of safety during construction. Stockman expects to allow the
lake to begin refilling later this year, as soon as the foundation
work is completed.
"That lake has huge economic impacts for the central
part of South Carolina, and we were mindful of that,"
said Brian Duncan, public affairs coordinator for SCE&G.
"That is one reason we wanted to do the work, do it safely,
but do it as quickly as possible."
The abutments have a soil core topped with sand and gravel
filters. On each side of the abutments, crews placed 5.5 million
cu. yds. of 30-in. or smaller shot rock from an onsite rock
borrow area. The borrow area will become an ash landfill for
the coal plant at the completion of the project.
The center section of the dam sits on a bedrock foundation.
During excavation, crews encountered crevices that were deeper
than anticipated that required remedial measures to fill the
crevices or trenches prior to placing RCC concrete. Barnard
used 30,000 cu. yds. of conventional concrete mix to fill
the crevices. Excavation went as deep as 70 ft., 50 ft. below
the nearby river.
"The bedrock was not as uniform as we anticipated,"
Stockman said. "We had to build retaining walls to address
the deeper excavations."
Crews constructed cement-bentonite walls and soldier pile
and lagging retaining walls to accommodate the additional
depth of some of the foundations. During the process of wall
design, Barnard moved its crews to the other end of the structure
to continue work and maintain schedule. None of the difficulties
resulted in work stoppages. Excavation was completed in the
spring.
"Anytime you dig into an existing dam foundation, you
never know what you're going to find until you get to the
bottom," VanAmburg said. "As a group, we have changed
the schedule and plans and methods at least a half-dozen times.
You deal the hand you are dealt and move around and adapt.
We've been able to do that successfully."
Barnard uses a roller-compacted concrete mix design that
was developed during a preconstruction testing phase for the
concrete section of the dam. The use of waste ash from the
coal plant and aggregate from the onsite borrow area have
reduced the total project cost.
The RCC is placed through specialty placement equipment on
the lift surface and then spread with bulldozers and ultimately
compacted with smooth-drum vibratory rollers. No steel reinforcement
is used.
"We are depending on the mass to hold back the lake
should it ever become an active dam," Stockman said.
Crews can place 500 to 600 cu. yds. an hour, or 8,000 cu.
yds. in a day. The pours are completed in 1-ft. lifts. Workers
place 15 in. of concrete at a time, and the rollers compact
it to 12 in.
Barnard can complete up to nine 1-ft. lifts in one day.
At the base, the concrete section of the backup dam is 160-ft.
wide and at the crest, 20-ft. wide. The midsection will be
a sheer, vertical, 150-ft. concrete wall on the lake side
and terraced on the downstream side. Work continues on the
center section.
"We have a long way to go, but we proved as a team that
we can get through it," VanAmburg said.
Project Team:
Owner: South Carolina Electric
& Gas, Columbia, S.C.
Construction Manager: Paul C.
Rizzo Associates, Columbia, S.C.
General Contractor: Barnard
Construction Co., Bozeman, Mont.
Dewatering Contractor: Griffin
Dewatering Southeast, Houston
|