|
The Chattahoochee Wastewater Tunnel
$114 Million Project Scheduled for Completion in December
By Scott Judy
Several major tunnel projects are under construction in the
greater Atlanta area, and one of the bigger ones, the Chattahoochee
Wastewater Tunnel in Cobb County, is heading toward completion.
Lyman File, project manager for Gilbert/Healy, called it
"just a big pipe in the ground," but the project
that started more than four years ago is slightly more than
that. At the time the contract was awarded, it was the largest
project Cobb County Water System had ever undertaken, and
it includes excavating a 49,600-ft.-long rock tunnel 100 to
350 ft. deep.
Approximately 47,500 ft. of 18-ft., 4-in.-diameter tunnel
was excavated using two tunnel-boring machines, or TBMs, and
2,100 ft. was excavated by drill-and-blast methods.
Gilbert/Healy, a joint venture of Kiewit-subsidiary Gilbert
Southern Corp. of Atlanta and S.A. Healy Co. of Lombard, Ill.,
is serving as the general contractor for the $114 million
project, which is being built to add capacity to Cobb County's
wastewater treatment system. (Gilbert Southern actually bought
out Healy's stake in the venture at its request about two
years ago but is continuing under the contractual name of
Gilbert/Healy.)
Jordan Jones & Goulding of Norcross, Ga., was the design
engineer. Parsons Engineering Science and Jacobs Associates,
both of Atlanta, are serving as construction managers.
The Project
Gilbert/Healy began work in June 2000. The original completion
date was April 2004 but has since been moved to December.
That delay was actually the result of finding different-than-expected
rock conditions underground and a consequential increase in
the amount of concrete tunnel lining required.
"The rock was of a significantly higher quality, with
fewer bad features, than we anticipated," said Steve
McCullers, engineering manager for Cobb County Water System.
"We had anticipated running into seams of unstable rock.
We ran into very much less of that."
Encountering less stable rock would require Gilbert/Healy
to set up "steel sets" to reinforce the tunnel,
a process that could slow down the team's progress.
Still, while encountering a greater amount of this harder
rock did enable the mining teams to maintain a more consistent
work effort, it also had a negative impact.
"It hindered the mining because it was harder and more
massive than originally anticipated," File said, adding
that the mining process took longer than originally expected.
Gilbert/Healy used two custom-built TBMs launched at two
separate sites. Both were supplied by The Robbins Co. of Solon,
Ohio. One started from the southern end of the tunnel, at
the Elizabeth Lane shaft, and proceeded north approximately
4 mi. The other launched from the Circle 75 shaft, an access
point at roughly the tunnel's midpoint, and headed north for
the remaining 5 mi.
As the TBMs progressed, the excavated material would then
be hauled out of the tunnel by a conveyor system that would
eventually go up and out of the shaft, where a stacking conveyor
would then stockpile the material.
Crews worked two 10-hour shifts per day, with daily four-hour
maintenance periods required to change the TBM's lubricants,
cutting heads and other items. Major maintenance took place
each Saturday and Sunday.
David Hamilton, project engineer for Gilbert/Healy, said
the Circle 75 shaft TBM mined an average of about 500 ft.
per week, versus the Elizabeth Lane TBM's 350-ft.-per-week
rate. Rock conditions made the difference.
"There were no steel sets," Hamilton said of the
Circle 75 shaft. "We didn't have any soft ground. We
didn't have to stand steel. That slows down the progress quite
a bit."
Hamilton was referring to the temporary ground support systems
that are put into place to enable the contractors to reinforce
and brace the newly formed rock tunnel.
The Elizabeth Lane TBM broke through at the Circle 75 site
in October 2002 to complete the connection. The machine that
started at the Circle 75 site wrapped up in December 2002.
Water Extends Schedule
As the project progressed, the amount of underground water
leakage was found to be more pervasive than anticipated, and
consequently the amount of tunnel lining was increased significantly.
"We had anticipated lining about 55 percent of the tunnel
to keep water from leaking in - thinking that 45 percent of
the tunnel would be basically dry," McCullers said. "We
thought it would be reasonably solid."
The more extensive water leakage caused the owner to increase
the lining to about 75 percent, roughly equal to an additional
10,000 ft. of tunnel.
Lining the tunnel would be its own trick. The concrete mix
would first have to be delivered 100 to 350 ft. down the shaft
and then conveyed as much as several miles before being placed
along the tunnel walls.
"The biggest issue for us was the longevity of the mix,"
File said. "We needed a mix that had a lot of shelf life."
Gilbert/Healy worked with local concrete supplier Thomas Concrete
and admixture manufacturer Master Builders to design the mix.
"We used a retarding admixture as well as one of the
new generation, high-performance plasticizers to control the
slump of the mix," File said. "We worked very closely
with Thomas to develop it. It was a beautiful mix."
He added that though specifications called for a 4,500-psi
concrete, the mix is delivering compressive strengths of more
than 6,000 psi.
Geotechnical
Both owner and contractor said an extensive geotechnical
report kept surprises to a minimum and contributed to a more
successful project.
"Tunneling is a very risky business," File said.
"And the more owners invest in geotechnical exploration
up front, the more comfortable contractors are in being able
to define the risks on a project.
"We think the owner had a very good geotechnical baseline
report, and it was fairly interpreted. A lot of times (owners)
have a lot of data but they have very conservative conclusions.
We do not stray far from what they present as the baseline."
McCullers said the agency thought it was a prudent investment.
"We did a tremendous amount of advanced geotechnical
work - much more than the norm for a tunnel of this nature,"
he said. "It really reflected in the bids. We felt like
it'd be better to spend an extra $1 million up front and get
the bids reduced by hopefully several times that, and have
a much more stable project with no surprises.
"It's been a pretty smooth project," McCullers
continued. "Everybody's going to make some money. We're
going to get a project under the money, and we're going to
get more project than we bid."
And Hamilton added: "It's a pretty successful project
for us. We're delivering a project on schedule and we're meeting
our budget.
Useful Sources:
For more information about this project, readers may visit
www.chattahoocheetunnel.com
Project Team:
Owner: Cobb County Water System
General Contractor: Gilbert/Healy, a joint venture of Gilbert
Southern, Atlanta, and S.A. Healy Co., Lombard, Ill.
Design Engineer: Jordan Jones & Goulding, Norcross, Ga.
Construction Manager: Parsons Engineering Science, Atlanta
Construction Manager: Jacobs Associates, Atlanta
|