|
Building Blythewood High School
$32 million project features wealth of amenities
By Bea Quirk
Blythewood High School in Richland County, S.C., won't open
until fall 2005, but it's already a site to behold.
The two-story, 298,000-sq.-ft., two-story building partially
wraps around a natural pond, which is also part of the site's
drainage system, and features lots of windows and skylights
for picturesque views of the pond and surrounding woods.
Its impressive list of amenities includes two academic (classroom)
wings, meeting rooms, music rooms, labs, workrooms, administration
offices, kitchen/cafeteria, media center, cyber café,
an auditorium, two gyms and locker areas, plus student and
faculty parking lots, baseball, softball and soccer fields,
a track, practice field and tennis courts.
The $32 million school is designed to eventually hold 2,000
students and is coming in at a cost of $98 per sq. ft. It
should be completed and open in the fall of 2005.
"It's one of the most complicated schools I've ever
built," said Leland Reynolds of H.G. Reynolds Co. of
Aiken, S.C., one of four prime contractors working on the
site. "But it's also going to be one of the most impressive
schools in the state."
Forrest King, project manager for construction manager Southern
Management Group in Columbia, S.C., called it "a functional
yet elegant building."
A tightly controlled, detail-oriented construction management
process headed by Southern Management Group has enabled the
project to stay on track and under budget. While quality has
always been a prime concern, Southern Management has used
every trick of the architectural, construction and engineering
trades to get as much bang for the buck as possible.
The total bond package approved by Richland County voters
was $52.1 million, which included the costs for both the school
and a multischool football stadium located on the same site.
The first step was to split the bond into two separate projects.
The stadium, costing $3.4 million, opens this fall and was
handled by a single contractor, Tyler Construction of Columbia,
S.C.
The school was designed by a partnership between The Boudreaux
Group of Columbia and Perkins & Will, a national firm
with extensive school experience. They have remained intensely
involved in the construction.
But even before design specs were completed, Southern Management
bid out the initial sitework. L. Dean Weaver Construction
Co. of Pamplico, S.C., began work in August 2002, and building
contractors took over the site in January 2003.
By that time, Southern Management's tight control was apparent.
Much of the 138-acre site is wetlands, so site designs had
to be reviewed and approved (plus remediation efforts undertaken)
by the U.S. Army Corps of Engineers and the South Carolina
Department of Health and Environmental Control.
Although this process often delays projects, Weaver was able
to use existing logging trails to get to the site to undertake
some work even before final approvals were received. As part
of the remediation agreement, much of the site will remain
undeveloped, and additional trees were planted.
Site drainage was a major challenge, said David Lindsay,
Southern Management's project director. "It's a very
flat site with a high water table and a lot of moist soils,"
he added. "It required extensive drainage structures."
That included modifying the shape of an existing pond and
using it as part of the drainage and irrigation system.
"Changing that pond didn't come cheap, but it was worthwhile,"
Lindsay said. "It will contribute to the long-term health
of the building."
Lindsay said Southern Management's attitude was, "Every
challenge has a solution - it's a matter of finding it."
He said that when initial construction bids came in over
budget, the team took a focused approach to find $2.5 million
in cost avoidances, including streamlining wall and glazing
systems, analyzing sizes of space and "looking at everything
from a true value-engineering standpoint."
For example, when looking for the most efficient mechanical
system, the team decided to go with a hybrid system and had
a self-contained customized penthouse system built offsite
by Trane.
Because of the cost savings generated, some high-end touches
have been added. The exterior features glass and both aluminum
composite and metal wall panels, as well as three different
colored bricks for accent bands. Most of the floors in the
common areas will feature epoxy terrazzo rather than typical
vinyl tile.
Bids for the high school project were sent out for single
and multi-prime contractors. The multicontractor bids came
in cheaper. "We are the coordinator and the facilitator
among all the primes, the owner and the architect," Lindsay
said. "That meant a general contractor didn't have to
play that role and so less project management hours were needed,
leading to a lower bid."
Timing was good, too. "We hit the market at the right
time," he added. "Contractors were hungry for work,
and it was before the spikes in the cost of steel and petroleum."
The four primes are Reynolds as general contractor; Burris
Electric Co. of Lexington, S.C., electrical systems; W.B.
Guimarin of Columbia, plumbing and HVAC; and Thompson &
Little of Fayetteville, N.C., food service and kitchen equipment.
With four contractors working onsite with an average of 150
workers, Southern Management has its hands full coordinating
the construction process. Yet it has been able to keep change
orders to a minimum.
"Every request or change goes through us, so we know
everything that's going on," King said. "We thoroughly
document everything in our daily reports. We also monitor
progress, review safety issues and assist the architects in
quality control."
Lindsay added: "We are a clearinghouse for everything,
but we also have an active, involved and intelligent team.
It's not a one-sided thing - it's a true team effort among
the contractors, owner and architects."
|