|
Progress Report: K-12 Overview
Overall school market expected to stay strong
throughout Southeast
By Scott Judy
K-12 school construction remains a strong focus for contractors
throughout the region, and for those who do their homework,
the results can be rewarding.
That's not to say that every assignment is a cakewalk. Margins
can be low, owners demanding, competition fierce and schedules
outrageous.
But in Georgia and the Carolinas, this market remains one
of the most consistent and strongest overall. For example,
McGraw-Hill Construction reported that approximately $2 billion
worth of K-12 school contracts were initiated in 2003 in these
three states, a figure that has been fairly steady since 1999.
"There's a ton of activity," said Ed Siquiera,
senior project manager for Winter Construction Co. of Atlanta.
"We can't bid them fast enough, considering how much
work there is out there."
Winter Construction is currently building the $27 million
Oconee County High School in Bogart, Ga.
While many contractors are looking to fill any gaps in their
portfolios resulting from declines in other markets, the firms
already doing this work aren't too worried about a lack of
opportunity.
"If you look at the population studies and the demographics
of the metropolitan counties, the growth in that age group
is really going to force the school systems to have to keep
up," said Jay Porter, vice president of Evergreen Construction,
also in Atlanta. "As long as people keep moving to the
area and they keep having kids, and the kids outnumber the
schools, that market will still be wide open."
Among the projects Evergreen is currently working on is the
$13 million Duluth Senior High School in Duluth, Ga.
Some Hot Spots
Atlanta is certainly one of the strongest regional areas
for K-12 school construction. That's where Skanska USA Building
is wrapping up its $55 million Alpharetta High School project
in Alpharetta, and where E.R. Mitchell Construction Co. is
overseeing the construction of the new $20 million Sandtown
Middle School, also in Fulton County.
There, as in other Georgia counties, school construction
is funded through SPLOST, or Special Purpose Local Option
Sales Tax, a 1 percent sales tax that runs for five years
and is often used exclusively for schools.
"If we didn't have SPLOST, we'd have to have bond referendums
or rely on state funding," said, Daniel Sullivan, director
of construction for Fulton County Schools.
With SPLOST, "We're building schools at a fairly good
clip" throughout metro Atlanta, and some area counties
are gaining more than 3,000 students a year, he added. "All
of our surrounding counties are growing rapidly. I don't see
it dropping off for school construction in the next five years."
Fulton County currently lets most of its projects as construction-management
contracts and is seeing plenty of competition for every school
it announces.
"Usually we have no fewer than 11 contractors apply
as construction managers," Sullivan said.
The backlog of projects and the fierce competition aren't
limited to Atlanta. In Charlotte, Bovis Lend Lease is serving
as the program manager for a $1 billion Capital Improvements
Program for Charlotte-Mecklenburg Schools.
This multiyear program, which runs until 2007, includes the
construction of 18 new schools, eight replacement schools
and 14 substantial-replacement schools, as well as the renovation
or expansion of 74 of Charlotte's 148 public schools.
Tony Ansaldo, director of architecture for Charlotte-Mecklenburg
Schools, said funding for CMS varies annually but has remained
in the $100 million to $200 million range for the past several
years.
Statewide, North Carolina has experienced some significant
and mostly negative variations recently. In 2001, for example,
the value of K-12 school contracts declined by 18 percent.
The next year, the market recovered only 2 percent, and then
went back down 22 percent in 2003 to a value of roughly $569
million. Contractors can sense this fluctuation in the marketplace.
"North Carolina as a whole has done a good job of providing
funds - probably not as much as parents, teachers and contractors
would like," said Joel Tucker, senior project engineer
for Skanska USA's $18.5 million Ronald Wilson Reagan High
School project in Winston-Salem. "I feel like there's
money out there. But it seems as though it's been spotty."
Regardless, there are numerous major projects under way currently
in North Carolina. Some of the bigger ones include the $24
million Dudley High School that Lyon Construction is building
in Greensboro; the $20 million Community House Middle School
Sorensen Gross is constructing in Charlotte; and the $17 million
Simon G. Atkins Academic and Technology High School in Winston-Salem
that New Atlantic Contracting is building.
In South Carolina, the big story is in Greenville County,
where that school district is in the middle of its four-year,
nearly $800 million program to revamp its 72 schools. Overall,
roughly two-thirds of the projects are completely new schools,
while one-third are renovations and additions.
It's a nationally unique initiative, with funding coming
from bonds sold by a non-profit organization formed especially
for this effort known as BEST, or Building Equity Sooner for
Tomorrow.
Institutional Resources of Greenville, S.C., the program
manager for the effort, proposed the concept several years
ago. Upon Greenville County's acceptance of the plan, BEST
then sold $860 million worth of bonds to fund school projects.
The school district then will use property-tax revenue to
pay off the bonds over the next 26 years.
"We've got a lot of work," said Don Buck, CEO of
Institutional Resources, adding that the firm has strived
to spread the work around. "But we've tried to award
it and package it such that all sizes of contractors can bid
on the work."
He said packages are put together with ranges varying from
$2 million to $5 million, all the way up to $70 million to
$100 million. Even so, it appears many projects are going
to out-of-town contractors.
"There's not been a lot of local (general contractors)
going after projects besides us," said Don Nickell, group
vice president with Greenville-based Suitt Construction. "And
I'm not quite sure why that is. Most of the firms that have
been going after and getting the schools have been from out
of town."
Even so, Nickell said the massive effort has been a major
boon to the local construction economy.
"Although most of the generals are coming from out of
town, the bulk of the subcontractors and the vendors are still
in the upstate part of South Carolina," he added. "There
is a huge economic impact to them."
Buck said that, to date, the program is on budget and on
schedule to conclude in time for the fall 2006 school year.
Prototype school designs, bulk purchase of materials and the
extensive use of precast concrete have benefited the cost
and schedule goals, he added.
Fueling this major initiative in Greenville County - as is
the case everywhere - is the obvious need for more and better
schools.
"Given the size of the bond issue and just the magnitude
of the program, you can imagine the condition that the schools
were in prior to this," Nickell said. "$800 million
worth of schools - that's a huge number for a county as small
as ours. You can imagine the education facility needs that
were in the county."
The BEST program will benefit Greenville County long after
current needs are met.
"In June 2006 the county will have 70 brand new schools,
practically, and a great learning environment and high teacher
morale," Buck said. "Those are positive aspects
that companies look at when they move to a community. It's
going to have a great impact on the economic development of
Greenville County overall."
Back to top
Alpharetta High School
Cost: $55 million
Location: Alpharetta, Ga.
Owner: Fulton County Schools
Architect: Perkins & Will Architects, Atlanta
Construction Manager: Skanska USA Building, Atlanta
Start Date: August 2002
Completion Date: June 2004
Project Description: This 335,000-sq.-ft. school sits on approximately
77 acres, of which roughly 60 are cleared. The mostly three-story
facility consists of a central spine area that includes three
classroom wings as well as a separate gym and performance
building. The new school will accommodate about 1,800 students.
The bulk of the school was built with a primarily steel structure
and masonry façade, though the gym utilized poured-in-place
concrete.
Phasing of the project was an important part of achieving
the schedule, said Clinton Boyd, senior project manager for
Skanska USA Building.
"The school is basically linear and there's a main portion
of the building that's essentially the center," he said.
"There's a small wing on the south end of the main building
that is the special education center for North Fulton County.
"We started in the main part of the building, which
houses the kitchen, and some of the career-tech areas that
were certainly more complex than the typical classroom wings.
From there, work flowed back into that south wing and then
we brought up the three house wings simultaneously. They were
all running concurrent, and at any one point in time, we had
five areas of the building under way."
The project's phasing in this manner demanded much from the
subcontractors.
"When we originally bid the job, it was demonstrated
to the subs that they had to be working in a minimum of five
areas of the building at once," Boyd said. "And
each one of those areas would require a full crew."
To accommodate the school's significant athletic facilities
- including a football field with stadium seating, football
practice field, softball facilities, baseball fields and tennis
courts - the design utilized a tiered site that required approximately
200,000 sq. ft. of modular retaining wall.
"There's over 100 ft. of elevation change from the lowest
part of the site to where the building sits," Boyd said.
He added that the wall is a composite between block wall and
earthen palisades wall.
Plateau Excavation handled all of the sitework, and Wall
Technologies installed the series of retaining walls.
Back to top
Sandtown Middle School
Cost: $20 million
Location: Atlanta
Owner: Fulton County Schools
Architect: Stevens & Wilkinson Stang & Newdow, Atlanta
Construction Manager: E.R. Mitchell Construction Co., Atlanta
Start Date: December 2002
Completion Date: June 2004
Project Description: Sandtown Middle School is the seventh
of a new prototype middle school designed for Fulton County
Schools.
The design of Stevens & Wilkinson Stang & Newdow
is organized around a tandem corridor system that links public
zones such as rotundas, cafeteria and common areas with the
academic areas. The media center is in the middle of the school,
with five instructional wings around it.
The 179,800-sq.-ft. steel-frame structure features a brick
veneer exterior and a modified bitumen roof system with arched
metal roofs at the gymnasium, cafeteria and media center.
The school will include 51 standard classrooms, 12 science
labs and 20 special-purpose classrooms.
Back to top
Oconee County High School
Cost: $26.8 million
Location: Bogart, Ga.
Owner: Oconee County Board of Education
Architect: FJ Clark Inc., Anderson, S.C.
General Contractor: The Winter Construction Co., Atlanta
Start Date: February 2003
Completion Date: July - November 2004
Project Description: Winter Construction Co. is heading for
a July completion of the first phase of this 235,000-sq.-ft.
school in Oconee County, Ga. The first phase includes the
classrooms, administration, cafeteria and gymnasium.
By November, the contractor expects to wrap work on a full-service
fine-arts auditorium facility that will be used by the school
and community alike.
Ed Siquiera, senior project manager for Winter Construction
Co., said the use of structural steel made the project unique.
"Most schools we deal with are basically masonry construction,
but this one was all structural steel, except for the small
P.E. building, which was concrete masonry units," he
said, adding that the team was able to avoid cost increases
related to steel. "We were fortunate. We were able to
get the majority of the steel purchased and actually on the
site well before that escalation really became an issue.
"We were probably taking the last bits of the fine-arts
building - which is the last building on the job - in March
of this year, so the majority of the material was already
procured."
Contributing to the uniqueness of the facility is the shared-use
nature of not only the fine-arts building but other amenities
as well, which Siquiera said could be a trend.
"Definitely for this facility they did some things with
the intent that it was going to be used for the community
and the surrounding area," he said. He added that the
school features 11 tennis courts and "the intent is to
have a tennis facility that would serve the entire community's
needs."
Back to top
Lee County High School
Cost: $20 million
Location: Sanford, N.C.
Owner: Lee County Board of Education
Architect: Boney PLLC, Raleigh, N.C.
General Contractor: J.M. Thompson Co., Cary, N.C.
Start Date: November 2003
Completion Date: August 2005
Project Description: This 179,500-sq.-ft. facility will feature
one main academic building as well as a football stadium with
press box. Claude Medlin, senior project manager for J.M.
Thompson, said the construction team divided the main academic
building into seven different wings.
Most of the wings are being built one-story high, while two
are two stories. The structure consists of a steel frame with
masonry walls and brick masonry veneer and some metal panels.
Roughly half of the new school's roof is a single-ply membrane
flat roof and the other half a sloping metal roof.
Medlin reported recently that the structural steel frame
erection was continuing, and no cost impact has been felt
by the owner. He said some steel materials such as steel pipe
and metal studs were stored at the project well ahead of time,
and so there have been only "minor impacts."
Back to top
Ronald Wilson Reagan High School
Cost: $18.4 million
Location: Pfafftown, N.C.
Owner: Winston-Salem/Forsyth County Schools
Architect: Walter Robbs Callahan & Pierce, Winston-Salem,
N.C.
General Contractor: Skanska USA Building, Winston-Salem.
Start Date: June 2003
Completion Date: June 2005
Project Description: This 194,200-sq.-ft. facility near Winston-Salem
is being built with a concrete masonry frame and brick veneer
exterior. The two-story classroom sections include a main
building with three additional academic wings.
Joel Tucker, senior project manager for Skanska USA Building,
said recently that the project was on schedule.
Like other new schools in the Southeast, this one features
its share of athletic amenities. Tucker called the school's
stadium "spectacular," and said it will also include
a full-size track and baseball and softball fields.
The owner and architect "have done a good job of anticipating
future growth," and the facility is ready for future
expansion, Tucker added.
Back to top
Cherrydale Elementary
Cost: $9.1 million
Location: Greenville, S.C.
Owner: Greenville County School District
Architect: McMillan, Smith & Partners, Spartanburg, S.C.
General Contractor: Suitt Construction Co., Greenville, S.C.
Start Date: August 2003
Completion Date: July 31, 2004
Project Description: This project - one of dozens under way
in Greenville County - includes a combination of new academic
and administration buildings as well as renovation of the
existing gymnasium. Paul Reach, project manager for Suitt
Construction, said the new facilities will provide classrooms
for kindergarten through fifth grades, science labs and a
cafetorium.
Reach said the structure consists of a combination of steel
and poured-in-place concrete, with the exterior featuring
precast architectural inlay brick panels. Reach added that
the schedule of less than one year to complete the project
was "extremely aggressive."
Suitt's interaction with the program manager, Institutional
Resources, has been positive to date, said Don Nickell, group
vice president.
"They have been very pleased with our effort, our project
team and the quality of our work," he added. "We've
been very satisfied with our dealings with them as well."
Back to top
|