|
Widening Interstate 75
GDOT Leading Effort to Widen Interstate in Southern Georgia
By Scott Judy
Like most interstate highways in the Southeast, Interstate
75 in southern Georgia is in great need of additional capacity,
and the Georgia Department of Transportation is in the midst
of reconstructing the highway from State Road 133 in Valdosta
to the Crisp/Dooly county line.
GDOT has divided the project into eight individual contracts.
Overall, it will consist of widening the congested highway
to six lanes, resurfacing existing pavement, installing a
median barrier and raising existing overpass bridges to provide
a minimum vertical clearance.
Douglas Asphalt Co. of Douglas, Ga., won two of the first
three contracts awarded, for a total of nearly 30 mi.
The two contracts included a $54 million, roughly 15-mi.
segment stretching across Crisp and Turner counties, and a
14.5-mi. section in Lowndes County totaling roughly $75 million.
The Crisp/Turner project, now nearly complete, started in
July 2001. The Lowndes County contract started in May 2002
and is scheduled for completion in March.
Crisp/Turner: Straightforward
Since the existing roadway on the first project in Crisp
and Turner counties was mostly asphalt, the job here was to
mill off the existing friction course, inlay with a new layer
of asphalt and then widen.
The sections of new roadway are built upon a 12-in. graded
aggregate base, with 12.25 in. of new Superpave asphalt. Scott
Chambers, area engineer with GDOT, said this new pavement
was usually placed in seven lifts, with four different mix
types: 6 in. of a 25 mm aggregate mix, 4 in. of a 19 mm mix,
1.50 in. of a 12.5 mm stone matrix asphalt (SMA) and 1.25
in. of new friction course.
According to GDOT, the aggregate required for the SMA section
is more coarsely graded and has less fines than other mixes.
"We had a little difficulty in obtaining the SMA rock,"
said Kyle Spivey, operations manager for Douglas Asphalt.
"The materials supplier had trouble getting the rock
approved, and that delayed the completion some."
The contractor will eventually be placing the same aggregate
as part of the Lowndes County project, too.
Douglas Asphalt used Blaw-Knox pavers and placed mats ranging
from 12- to 18-ft. wide, with most of the wider pavement being
laid for the new lane. The paving contractor also used Blaw-Knox
and Roadtec material-transfer devices to feed the hot mix
into the paver.
The project included the jacking of roughly six overhead
bridges and superstructure replacement on one mainline bridge.
Bellamy Brothers performed the bridge jacking.
"We had to raise the overhead bridges in order to maintain
a minimum vertical clearance," Chambers said. "The
bridge sub came in and built some jacking piers and basically
put out a bunch of hydraulic jacks and raised the existing
bridge up."
Chambers added that most of these bridges were raised an
average of about 6 -7 in. "We jacked them, usually about
an inch at a time, and we'd pave up 1 in. to the new elevation
of the bridge. So we put additional asphalt on either end
of the bridge."
Spivey added that Douglas Asphalt "worked 24 hours a
day, most of the time, during the grading and dumping of the
base stone."
Even so, Chambers said the project was somewhat behind schedule
and was headed for a late June completion.
Lowndes County: Concrete Rehab
The Lowndes County project was considerably different. About
two-thirds of the 15-mi. project featured existing concrete
pavement, with significant amounts of it requiring rehabilitation
before a new asphalt pavement was placed.
"We basically went in and tore out a bunch of the old
concrete slabs that had busted and cracked and spalled, and
we poured new slabs in and doweled into the existing pavement,"
Chambers said. Michigan-based Causey handled this work.
Spivey added that once the contractor started working the
project, the team found that the amount of rehabilitation
required exceeded GDOT's initial estimate.
The existing concrete averaged roughly 7-8 in. deep. Once
the old concrete was torn out and the new slabs placed, Douglas
Asphalt overlaid it with approximately 9.25 in. of asphalt.
For the one-third of the project that was already asphalt,
the contractor milled off the existing friction course and
placed 7.5 to 8 in. of new asphalt.
Paving over the rehabbed areas was difficult, Spivey said.
"We had a little trouble getting the compactions there,"
he added. "We worked with the state trying to get the
compaction right. We finally had to (increase) the AC content."
Like the Crisp/Turner project, the new lane is built of approximately
12.25 in. of asphalt atop a 12-in. graded aggregate base.
Design-Build
The two Douglas Asphalt contracts were unusual for GDOT
in that they were let as design-build. On both, the paving
contractor teamed up with designer Wilbur Smith Associates
of Columbia, S.C.
Some of the differences between these and other contracts
was that the state did not always provide project specifics,
such as quantities, which is usually the case. At the same
time, GDOT provided a strict specification for the mix design.
"We gave them a typical section and told them this is
what we wanted," Chambers said.
The biggest difference was in the culture of design-build.
The two jobs were Douglas Asphalt's first design-build contracts
with GDOT, and the department's experience with the process
is also limited. Even so, Spivey said the effort was mostly
smooth.
"Sometimes there might be some delays in the approval
process, but it (design-build) gave more of an atmosphere
of partnering with the DOT," he added. "There was
good cooperation. The DOT had good qualified people, and it
went well. The good parts of it outweighed the bad."
As for Douglas Asphalt's performance, Chambers said, "The
workmanship has been pretty much on par with the work they've
done for us in the past."
Project Team:
Owner: Georgia Department of Transportation
General Contractor: Douglas Asphalt Co., Douglas, Ga.
Designer: Wilbur Smith Associates, Columbia, S.C.
|