|
A Work of Art at the High
Contractors building $85 million
addition at Atlanta's High Museum
By Debra Wood
Atlanta's High Museum of Art at the Woodruff Arts Center
will more than double its exhibit space with the addition
of two new gallery buildings at its midtown campus.
"The museum has been extremely successful," said
Marge Harvey, director of architectural planning and design
for the High. "We've had unprecedented growth in attendance,
membership and our collection. We decided we needed to expand
to provide our visitors with better amenities. We also needed
dedicated special-exhibition galleries."
More than a half a million people visit the 135,000-sq.-ft.
High Museum annually, nearly double the number that visited
when the current building opened in 1983. About 40,000 households
belong to the museum.
With its space constraints, the museum could only display
about 3 percent of its permanent collection. The $85 million
addition will add 177,000 sq. ft.
Renzo Piano Building Workshop of Genoa, Italy, designed a
$130 million expansion plan for the Woodruff Arts Center in
collaboration with Lord, Aeck & Sargent Inc. of Atlanta.
The team conceptualized a unified, pedestrian-friendly village
for the arts, with a piazza and terraces, two gallery buildings,
an administrative building and a restaurant for the High.
One of the two gallery buildings is called the Wieland Pavilion.
The other has not been named, pending a donor.
The design also included a new residence hall for the Atlanta
College of Art and other improvements to the Woodruff campus.
Jones Lang LaSalle of Atlanta is the project manager. Randy
Shields, project director for Jones Lang LaSalle, said the
use of unique materials, such as the passive, natural lighting
system, and the tight, urban site on an operating arts campus
were obstacles during construction, but they have been well
managed.
"It's going great," Shields said. "There are
daily ups and downs, but if you lift yourself above that and
look at the big picture, it's going well."
A joint venture between Skanska USA Building and minority
contractor H.J. Russell & Co., both of Atlanta, serves
as construction manager for the High project.
"We are not building a typical, standard museum,"
said Willie Russell, project executive, who is no relation
to the minority contractor. "We've become more than bricks-and-stick
builders. We're part of the architectural climate. The museum
structure actually becomes a piece of art."
Skanska-Russell Project Director John LeFauve considers the
complex a living, breathing piece of sculpture. "The
owner made clear that quality is paramount and [the High]
wants the architect's vision to be realized," he added.
"And it had to open on time."
Harvey said even though the architecture may appear quite
simple at first, it is really a sophisticated design.
Holder Construction Co. of Atlanta completed the dormitory
project. The college needed the new residence hall before
Skanska-Russell could begin tearing down the existing dormitory.
Demolition began in summer 2003.
A sculpture building, subway platform and underground parking
garage also came down. The new underground parking complex
extends deeper into the ground, picking up space for an additional
100 cars.
"We had to do a lot of mass rock blasting and excavation,
and we were surrounded by the owner's buildings; Peachtree
Avenue, a major artery; and another street on the back side
with the public transport subway system," LeFauve said.
Skanska-Russell arranged for seismic studies before the blasting
and placed monitors throughout the existing museum to check
that the excavation was not creating any excessive movement.
The structures are reinforced concrete up to the piazza level
and structural steel above. Skanska-Russell began steel erection
on the largest building, the five-story Wieland Pavilion,
and then started on the smaller, three-story, special-collections
gallery. The work will run parallel until both top out at
the end of August.
Because of the tight, midtown site, Skanska-Russell instituted
a just-in-time delivery process. Special permits, with specific
routing, are required for deliveries at off-peak traffic times.
"We don't call for material until we are ready to put
it into place," LeFauve said.
An architectural concrete with reveals, pie-hole patterns
and surface articulations covers the exterior of the building
at street level. Glass-enclosed bridges will connect the new
buildings to each other and to the existing High Museum. Decorative,
vertical aluminum panels cover the balance of the structures
and will be added to the existing museum to help it blend
in. On the new structures, the aluminum panels continue to
the roof, where they twist and serve as sunshields for a rooftop
full of skylights.
"[The roof] is a ribbon of sunshades that goes over
the top of the light cones and down, then up and down,"
Harvey said. "It follows the skylights in a grid pattern.
It goes all the way across the top of the building and continues
down the other side of the building."
Early computer modeling, showing the sun field and weather
conditions throughout the year, detected that southern sunrays
could enter the gallery on certain days. The direct sun could
be harmful to the artwork.
"We had to change the geometry of those cone and shades
so there would never be direct sunlight," Harvey said.
In order to allow patrons in the upper galleries to view
the art under natural light, Renzo Piano added 800 skylights
to the main pavilion and 200 to the smaller structure. The
skylights are 3 ft. in diameter, with glass at the top. They
are placed adjacent to each other, tipped lightly to the north,
and rise about 4 ft. above the roof. A curved object that
acts like a hood blocks the southern light.
"[The architect] is using a very simple, elegant geometric
shape to control the way light enters through the skylights,"
LeFauve said. "It presents some unique and challenging
construction conditions for us."
Key contractors include Cleveland Electric Co. and B &
W Mechanical Contractors Inc. of Atlanta and Precision Concrete
Construction Inc. of Alpharetta, Ga. Between 300 and 400 workers
are onsite.
The project is on schedule for a summer 2005 completion.
The administrative building and parking garage will be turned
over this fall.
"We've been able to pull together tremendous subcontractor
resources for all these specialty items and still satisfy
the owner's budget and schedule needs," project director
Shields said.
Useful sources:
High Museum of Art http://www.buildingthehigh.org
Renzo Piano Building Workshop http://www.rpbw.com
Woodruff Arts Center http://www.woodruffcenter.org
|