|
Jacksonville's New Main Library
Joint Venture Team is Pushing Hard to Meet Tough Schedule
By Scott Judy
Libraries always have due dates, and usually they're more
than sufficient for the task at hand - reading a book. But
the Auchter-Elkins-Lodestar-Parris joint venture building
the $55 million new Main Library for the city of Jacksonville
is finding its due date rather restrictive.
For example, in May, just eight months from the completion
target of January,the construction team had just topped off
the four-story, 300,000-sq.-ft. structure designed by Robert
A.M. Stern of New York. With detailed brick and architectural
precast concrete still to be put in place on the high-profile
facility's exterior, and with high-end interior finishes such
as terrazzo floors, stone and elaborate millwork waiting inside,
the team has many goals to go before it rests.
"We're pushing it," said Jack Belt, senior project
manager and senior vice president with joint-venture participant
The Auchter Co. of Jacksonville. "It's aggressive, and
it's got a lot of challenges to it. We're taking the approach
that we need to get there."
Belt added the team has instituted its plan to have numerous
subcontractors work second shifts for many of the project's
various components, and that several of the firms involved
with the structure are working six to seven days a week.
The team mobilized in February 2003, about two months after
the city held its groundbreaking - and about four months after
the team had originally hoped to get started with foundations.
Despite the delay, the end date remained fixed at its pre-Super
Bowl timetable. Even so, Belt described the 24-month schedule
as "typical of all projects anymore. Everybody wants
it now. Right now it's not planned to be used for any (Super
Bowl) functions, but it would be a nice thing to point at
when visitors come to town."
While the city acknowledges the challenges the team faces,
it remains confident the contractor will meet the deadline.
"Jack is certainly correct - it certainly is an aggressive
schedule," said Rex Holmlin, a program principal for
the Better Jacksonville Plan and the city's main contact for
the library project. "Jack and his team are doing an
outstanding job. They're on a glide path to success."
Project Progress
That "glide path" has had its bumps along the way.
First, the team experienced the four-month delay at the beginning,
and since then it has seen its cast-in-place concrete structure
rise somewhat more slowly than expected.
Local utility provider JEA has kept Duval Street - which
abuts the library project and is the main access point for
materials delivery - unavailable for longer than expected
due to its placement of a chilled-water line that will serve
the library.
Additionally, the costs of numerous standard building materials
have risen dramatically since the beginning of the project.
Though the joint venture had many of the materials ordered
and delivered at the old prices, supply has tightened greatly.
"It's an availability issue," Holmlin said, hinting
at the possibility for delivery delays of some materials.
For instance, he said though the city has a "very aggressive
direct purchase program," drywall allocation had become
an issue. Holmlin added that if it had started one year later,
the project - as it's being built now - would have cost significantly
more due to the rise in material costs.
As it is presently, the project is a result of considerable
input from the joint-venture team during design.
"We came in early, at some conceptual schematic stages,
and did a lot of early estimating," Belt said. He added
that the joint venture contracted with the city in fall 2002
and provided estimates during design development when documents
were at 30, 60 and 90 percent complete.
Belt didn't recall any major changes, but said, "The
list of recommendations hit all divisions." Subcontractors
"were all involved," with significant input from
mechanical and electrical firms, he added.
The coordination of materials deliveries is a major focus
right now, said Scott Humphrey, project superintendent for
Elkins. He added that approximately 75 percent of the project's
laydown area has been closed due to coordination with the
chilled-water-line installation.
"We spend a lot of time coordinating materials deliveries,"
he said. "We have charts. We have daily meetings that
are mandatory for all subcontractors. There's been a great
deal of cooperation with everybody."
Contents
The new main library will be roughly three times the size
of the city's existing facility and will feature numerous
amenity improvements. The city has great expectations.
"It will have a very significant effect, not only on
the downtown Jacksonville area but on the citizens of Duval
County," Holmlin said. With the inclusion of a 600-space
parking garage as part of the project, he said, "It will
be much easier for citizens to come down and use the library."
Based on similar projects in other parts of the country,
the city is expecting library attendance to double or triple
over current numbers.
Holmlin described the amenities as "phenomenal,"
citing the new children's area and theater. A 10,000-sq.-ft.
Grand Reading Room will sit on the top floor, underneath a
steel-domed, arching roof. An open-air courtyard is located
on the second floor of the building's southern elevation and
will include seating, landscaping and water features to produce
a tranquil space for library users.
One floor below the main ground floor, the library will feature
a conference level with meeting and conference rooms that
will be accessible from the building's rear entry off of Main
Street.
A monumental staircase will greet visitors from the library's
main Laura Street entrance, and terrazzo floors will make
up most of the main lobby and other areas. There will be a
significant amount of woodwork and crown molding, and some
Vermont marble will be used.
"The interiors are really a high level of quality, real
ornate but not ostentatious," Belt said. "I'm anxious
to see how a lot of this turns out."
Holmlin called the finishes high quality but functional.
Referring to former Mayor John Delaney, who shepherded passage
of the Better Jacksonville Plan that included the new library,
he added, "One of the previous mayor's promises was to
build only first-class buildings. This is going to live up
to that promise."
About the Builders
The main library was the only major vertical structure to
be awarded to a team of mostly local general contractors.
Auchter and Elkins have the majority of liability for the
project, though participation is divided equally among the
four parties: The Auchter Co., Elkins Constructors, Lodestar
and The Parris Co.
Though Auchter and Elkins are longtime and current competitors,
Humphrey said the team has "put all of our differences
aside." "The joint venture has worked out great,"
he added. "We all look at this as one company we're working
for."
Belt said everyone's focus is this job. "We have not
seen any kind of competitiveness (among the project team members)."
he added. He credited a similarity in philosophies between
the two longtime Jacksonville firms.
"Auchter's and Elkins' philosophy
is to give
the attention to the projects and the owners," he said.
"If we take care of the project, everything else will
work out."
Holmlin concurred.
"Both Auchter and the Elkins are very knowledgeable
and results-oriented," he said. "The personnel on
the job have melded together well, and their attention to
detail is outstanding. The AELP team is doing a great job."
Despite the optimistic comments, Belt and company know the
pressure is only going to intensify as the team heads toward
the conclusion.
"It is extremely high profile," Belt said. "Citizens
have a vested interest in this. And we're under a microscope.
The level of stress is going to increase. It's going to be
a sprint from here on out.
"It's probably the highest-profile job I've ever done,
even though I did City Hall and the St. James Building. The
city is going to have a facility they're going to be really
proud of."
The BJP funded renovations or improvements to numerous city
libraries, and the new main library will stand as the symbol
of the city's renewed investment in these facilities.
Holmlin, who is overseeing many of the projects, said: "This
is the flagship building, a project that citizens of this
county are going to be proud of for many, many years. They're
going to be wowed. And the firms (building it) are going to
have something to be proud of."
Project Team:
Owner: The City of Jacksonville
Architect: Robert A.M. Stern, New York
Construction Manager: Auchter-Elkins-Lodestar-Parris, a Joint Venture
Architectural Precast Supplier: Gate Precast, Jacksonville
Masonry Contractor: R.D. Masonry, Jacksonville
Steel Fabricator and Erector: Trinity Fabricators, Green Cove Springs, Fla.
|