|
The PAC's Second Act
The cast building the Performing Arts Center
is pledging to make beautiful music together
The $261 million Performing Arts
Center of Greater Miami will feature two separate buildings,
the 2,480-seat Sanford and Dolores Ziff Ballet Opera House
and the 2,200-seat Carnival Symphony Hall. It's currently
18 months behind its original completion date, but the principal
parties are vowing they're in harmony as they face the final
half of construction.
By Scott Judy
We open on the second act of a great and still unfolding
drama, the building of the Performing Arts Center of Greater
Miami.
Act one, which ran longer than expected, was the scene of
much strife and consternation. The owner, Miami-Dade County,
frustrated with significant construction delays and concerned
over its perception of ongoing quality measures, reportedly
asked the county attorney to investigate grounds for terminating
the contractor, Performing Arts Center Builders, a joint venture
of Odebrecht Construction, The Haskell Co. and Ellis Don.
"We are sounding the alarm now," Gail Thompson,
project director for Miami-Dade County, told Engineering
News-Record last fall. "We're putting their feet
to the fire to correct deficiencies and to develop processes
to avoid further lapses in quality."
By the end of March, however, as the first act came to its
symbolic close with the emotionally charged placement of the
last beam of 9,000 tons of structural steel, the principal
actors were arm-in-arm - on stage, at least - and they were
vowing that the audience hasn't seen anything yet.
"I feel as good about where we are as I ever have,"
Thompson said this spring. "I feel really good about
where we stand with the project and its direction. We're working
together."
Even so, the $261 million project is now heading for a spring
2006 completion, or about 18 months behind the original schedule.
Scene Change
Last fall, a couple of new actors were brought to the production,
both of whom have since emerged as leading characters. The
first was Bill Johnson, assistant county manager for Miami-Dade
County and a veteran of other major county projects such as
the Miami Heat Arena and construction at Miami International
Airport.
The second was Ron Austin of Ohio, who had been working as
a consultant to the project's joint venture contractor.
Johnson had been involved with the PAC project for numerous
years and was extensively involved in the design solicitation
that resulted in the selection of Cesar Pelli and Associates
of New Haven, Conn., as project architect nearly 10 years
ago. Johnson stepped away from the project during the construction
bid stage.
When Johnson came back to the project last fall, things were
about as bad as they could get. Construction was already estimated
to be about one year behind schedule, and the potential for
significant cost overruns - now pegged at $61 million in pending
change orders - hung ominously over the project. The owner
and contractor traded barbs in the press.
"There were three legs to the stool, and all three legs
had stopped communicating," Johnson said. "Everybody
was closed down. There was a lot of finger-pointing. And nothing
gets accomplished with finger-pointing. I had to restore a
sense of trust between the three sides and open up communication
again."
The starting point for improved communications was for the
contractor and architect to listen closely to the county.
"I'm the one paying, and I'm the one who wants to be
listened to," Johnson said he told the parties. "I'm
the owner. So if you want to continue to work with me you
need to listen to what I have to say. Simple as that. If you
don't want to listen, and you don't want to work with me,
then we'll just part company."
Until agreement was achieved on a viable work-out strategy,
Johnson told each party, "'No more money for you, Cesar
Pelli,' and 'No more approval of change orders, contractor.'
The owner was not going to lay back and be a patsy. I made
that very clear."
Almost immediately, Johnson hired national construction services
firm URS on an emergency basis to assess the situation and
point out areas for improvement - and not to point fingers.
Instead, the question he needed an answer to was "What
does it take for us, as a team, to successfully complete the
project?"
PACB - the joint venture prime contractor made up of Odebrecht
Construction of Coral Gables, Jacksonville-based Haskell Co.
and Ellis Don of Ontario, Canada - was evidently thinking
the same thing.
At roughly the same time it brought in Austin to help smooth
things out. Austin, president of Ohio-based Final Solutions
Management, had worked on several Pelli-designed arts centers
in the past and had been working as a consultant to PACB since
its pre-bid exploration of the project in the late 1990s.
Austin functions as PACB's liaison to the owner and architect.
Like Johnson, Austin is focused on improving communication
and is not at all interested in looking back. Listening and
improving understanding of the parties' respective expectations
is his focus now.
"As a group we are spending a considerable amount of
time trying to understand the expectations of the various
parties," Austin said. "We're spending a lot of
time going through the details and the understanding of the
expectations of the owner, the architect, the contractor and
the subcontractors to make sure that the ultimate product
that is delivered is commensurate with those expectations."
Randolph Volenec, onsite architect for Cesar Pelli, said
of the improved communications: "We've continued to try
to improve our ability to solve problems jointly, and do it
through a series of onsite meetings. The buildings are complex
and they're highly detailed.
"We continually have make sure all of the efforts are
directed toward maintaining that quality and delivering the
building that the county expects."
Lofty Expectations
The concerns were as great as they were partly because of
the project's lofty ambitions and complexities.
By any measure, upon completion, the Performing Arts Center
of Greater Miami will rise to a level of quality not attained
in many other structures in the Southeast.
"We're building two of the finest halls to open in the
early part of the 21st Century," project director Thompson
said. "We're building what will be the fourth-largest
arts center in the country, at the highest level of acoustic
excellence."
A premier acoustician, Artec Consultants of New York, is
overseeing the building's acoustics, and renowned theater
consultant Fisher Dachs Associates, also of New York, is lending
its expertise.
Indeed, this is not just another building project, such as
a condo, hotel or commercial office facility. The PAC's halls
must perform.
"It's always difficult for me to try to explain just
how complicated the construction is," PACB's Austin said
of these types of facilities. "It is not like any other
construction. It's more like building a fine musical instrument
than it is a building because you have to worry about things
such as acoustics, sight lines, the planning of the theater
and the architecture.
"If any of (those aspects) fail then the project is
not going to be a success."
Much of the complexity results from the intertwining of the
building's acoustical requirements and the need to isolate
the halls from the rest of the structure. Acoustical isolation
joints measuring 2 in. thick and containing filler material
will surround the halls in all directions, isolating them
from the rest of the facility. The building is being constructed
to the highest acoustic standards.
The design has created a production drama for the structural
steel work. "We're building a thin structure because
we want it to be intimate," Thompson said. "The
steel members need to be thin, but we also need to have clear
spans for sight lines. There are a lot of competing issues
that show themselves in unique structural configurations."
No two members are the same and unique shapes are common,
she added.
Structural steel erection began in November 2002 - 2.5 years
after demolition of the site's existing building first started
- and wrapped up in March. ADF International of Quebec performed
the erection work and earned favorable reviews from all parties
for its performance.
However, of the $61 million in pending change orders, approximately
$31 million relates to the structural steel work, which was
delayed in starting. PACB has contended it was delayed for
nearly a year in starting by design complexities. The owner
earlier asserted that PACB should have hired the structural
steel subcontractor earlier.
Community and Intimacy
The PAC is divided into two separate halls, with the 2,480-seat
Sanford and Dolores Ziff Ballet Opera House situated on the
west side of Biscayne Boulevard and the 2,200-seat Carnival
Symphony Hall on the east. In all, the facility will measure
approximately 570,000 sq. ft.
This physical straddling of Biscayne Boulevard reflects the
owner's and architect's goal to have the new facility incorporate
and connect with the surrounding community.
"This center needed to integrate itself into the city,
and be a part of the city," Thompson said. "(The
Pelli design) allows the city to essentially go right through
the project."
As the structure comes together, the quality of the halls
themselves is also becoming evident - a fact that could be
a real reason for the positive attitude pervading the project
at this time. Both reflect the immediacy and intimacy the
PAC will ultimately provide its patrons, and is an exciting
element to behold.
Thompson said that when critics of the project tour the site,
their remarks often soften at the impression the present construction
provides.
"What's incredible about it now is that it has taken
the form of what it will be ultimately, both in the exterior
and the interior," she added. "You go inside and
you see the shape, and you can feel the intimacy and the scale,
and the relationship between the audience area and the stage.
You're kind of blown away. You've seen nothing like it."
During a tour of the project in March, Thompson indicated
that the configuration of the two halls is approximately opposite
of traditionally designed performance halls. Whereas other
facilities traditionally use one-third of the space for the
stage and two-thirds for the audience, the PAC's layout is
just the opposite.
That layout will not only provide a heightened sense of intimacy
in the hall, it will also allow greater flexibility of the
stage, so much so that "dark" nights will not generally
be necessary, enhancing the PAC's revenue opportunities. The
size of the stage will enable it to be changed easily, either
during a single performance or between different shows.
Intimacy is also enhanced by the acoustical need of keeping
the floor-to-ceiling height as low as possible, Thompson said.
To get a feel for the emerging acoustics, Thompson said the
team recently had a soprano singer come in and perform.
"The hall isn't completed, but the acoustics are spectacular,"
she added. "The performance made everyone feel charged
up and energized.
"Whatever the challenges are, it just makes me feel
excited at the prospects of what we're doing and what it will
be at the end."
The Final Act
Achieving the vision of the once and future PAC will be the
tricky part. The project's next phases will likely test the
newly formed sense of teamwork and the improved communication.
"We are at a critical point in the project," Austin
said. "When we start the enclosures and we start the
interior finishes, it requires a tremendous amount of coordination
of material and manpower into a confined space."
The group is attempting to be as proactive as possible. For
example, Austin, architect Volenec and representatives from
the project's millwork subcontractor, Baron Manufacturing
of Pompano Beach, recently traveled to Madison, Wis., to visit
with principals on another arts center project.
"We listened to how they did it, what they found were
the pitfalls and how they corrected them," said Volenec,
who added that the PAC's millwork is still in shop drawings.
"We're trying to do everything we can to learn from others
who have gone through similar experiences."
Quality-control measures have been ramped up since last fall,
with regular meetings held between representatives of all
parties involved in the project. This quality-assurance team,
said Volenec, "is continually looking at the work that's
being put in place and making sure it's in compliance with
the documents and the requirements of the project."
Again, it comes down to communication, Thompson said.
"The bottom line with QC is first to make sure the architect's
intent and the intent of the acoustician and theater consultant
are clearly communicated and understood by everyone,"
she added.
And for all the strife over budget and schedule, the owner's
representative, Johnson, said those two aspects take a back
seat to quality.
"The No. 1 issue on the project isn't schedule, and
it really isn't even money," he added. "It's quality.
How the sight lines work. If we spend all of this money and
the acoustics don't work, it's a failure. It's a flop. So
the driving factor here for Gail and for everyone else onsite
is to ensure that what's being constructed is what was envisioned
and what is demanded."
Encore, encore?
During the week of the celebratory steel event in late March,
the parties came to an agreement that set May 2006 as the
new final completion date. In mid-April, however, the parties
were continuing to discuss other alternative plans, including
possible incentives and penalties for the contractor completing
ahead of or behind the new schedule.
The principal actors are, at least for now, in concert and
resolute that they'll achieve the uncompromised vision of
the PAC.
"The challenges are equaled by the excitement that these
projects build as you near completion, until when you have
the opening and everyone is just walking on air," Austin
said. "What I expect is a continued diligent effort to
get it completed."
Johnson certainly isn't letting any party off the hook. Only
$6 million in pending change orders have been approved to
date, and he said he is "aggressively pursuing"
mediation and the dispute-resolution process to address the
various parties' past grievances.
Even so, the story, for now, closes with key actor Johnson
remaining confident the quality will be there when all is
said and done.
"We intend to complete this facility as envisioned,
in a partnership," he added. "We are optimistic
and hopeful that our partners will remain with us.
"It's going to be great. It's world-class. It will be
a legacy for Gail, myself and for our generation over the
next several generations. I truly believe that."
Performing Arts Center of Greater Miami
Project Team:
Owner: Miami-Dade County
Construction Manager: Performing
Arts Center Builders, a joint venture of Odebrecht Construction,
Coral Gables, Fla.; The Haskell Co., Jacksonville, Fla.; and
Ellis Don, Ontario, Canada.
Architect: Cesar Pelli &
Associates, New Haven, Conn.
Acoustical Engineer: Artec Consultants,
New York
Theater Planning, Design and Lighting
Consultant: Fisher Dachs Associates, New York
Structural Steel Erector: ADF
International, Terrebonne, Quebec, Canada.
Additional Sources:
To review the Performing Arts Center of Greater Miami's "Briefing
Document for Agencies and Consultants" Click
here for MS Word Document >>
For an expanded version of Southeast Construction's interview
with Miami-Dade County Assistant County Manager Bill Johnson,
visit: www.southeast.construction.com/features/archive/0406_Feature4.asp
For the owner's and operator's view of the project, visit:
Miami-Dade Government: http://www.miamidade.gov/pac/home.htm
·Performing Arts Center Foundation: http://www.pacfmiami.org/index.html
Past media coverage of the project can be found at:
Engineering News-Record: http://enr.construction.com/news/buildings/archives/030922.asp
Miami Today: http://www.miamitodaynews.com/news/031009/story3.shtml
South Florida Community Development Coalition: http://www.floridacdc.org/articles/030511-1.htm
|