|
Monster Parking Garage
Contractors Joint Venture to Build
Unique $182 Million Car-Rental Facility
The joint venture of James A. Cummings Inc. and Centex
Rooney Construction Co. literally had to write its own addition
to Florida's Building Code when it started building the
$182 million Consolidated Rental Car Facility at Fort Lauderdale-Hollywood
International Airport. The massive concrete structure is
thought to be the only structure of its kind in the country.
By Scott Judy
Upon first glance, the Consolidated Rental Car Facility that
the joint venture of James A. Cummings Inc. and Centex Rooney
Construction Co. is building at Fort Lauderdale-Hollywood
International Airport looks like an overgrown version of the
parking garage sitting next to it.
It looks like a parking deck, and yes it holds cars, but
the nine-story CRCF is a lot bigger than most. At roughly
4.3 million sq.-ft. - equal to roughly 76 football fields
- it could accommodate an estimated 9,000 parking spaces.
It's oversized in scope, function and complexity, too. Think
of it as a parking garage on steroids.
Its extra don't include just some retail on the ground floor,
either. Instead, the CRCF's complexity comes mostly from its
first-floor function as a quick-turnaround (QTA) facility
for processing rental cars, including fueling, washing, some
maintenance and otherwise sprucing up.
Sixty-three gas dispensers and 126 nozzles - all of which
necessitated a unique foam-deluge system for fire purposes
- are located on the first floor, along with a car wash. It
will also include approximately 150,000 sq. ft. of retail
operations and supporting offices for car-rental firms using
FLL, all contained within a high-end lobby entrance evocative
of a hospitality facility.
Notably, all of this will be consolidated under one roof,
making the CRCF one of the very few - if not the only - facilities
of its kind in the nation.
"We believe we're the only truly consolidated rental-car
facility in the country," said Todd McClendon, senior
project manager for URS of Fort Lauderdale, the program manager
overseeing FLL's expansion. He added that a similar project
at Hartsfield-Jackson Atlanta International Airport will actually
have its quick-turnaround operations taking place outside,
on a large parking lot-type area.
"If we were just building a parking deck, we wouldn't
have nearly the challenges that we have," he added. "It
creates a whole bunch of special requirements."
Concrete Challenge
The joint venture of Fort Lauderdale-based Cummings and Centex
Rooney of Plantation is a follow-up act to the Hibiscus Parking
Garage project, located next door to the current project.
The two firms teamed to build that project several years
ago, completing it ahead of schedule and sufficiently under
budget to not only add amenities but also return an estimated
$1.4 million to the owner, the Broward County Aviation Department.
Leading the construction this time are two vets from that
past project, Geoff Bunnell, senior vice president with Cummings
(the lead firm), and Rob Gillette, senior project manager
for Centex-Rooney.
Bunnell reiterated the huge difference between this project
and the previous one.
"This one is much more than a garage," he said.
"A lot of people are saying, 'Well, it's just a parking
deck. If you're topped out, you're done.' That's not the case.
For example, the drywall and stucco contract on this job is
as big as it would be on a $35 million high school. There's
$4 million worth of HVAC on this project - the garage next
door's (HVAC work totaled) $200,000. The plumbing system on
this one is $3 million, and the fire-protection system is
$2 million.
"You don't see it because it's so big, but there's a
lot of work."
The sheer size of the project could be witnessed from the
beginning. H.J. Foundation of Miami started on the first of
2,774 auger-cast piles on Nov. 1, 2002. It concluded its work
about 31 mi. later.
By late December 2002, the project team was pouring its first
column, and the first elevated deck pour took place Feb. 5,
2003. It would be the first of nearly 12 months straight of
concrete work, not ending until Jan. 19, when the project
topped out, some 138,336 yds. of concrete later.
The team hoped to pour at a rate of 80,000 sq. ft. per week,
but actually achieved a rate of 100,000 sq. ft. per week for
a significant stretch. It peaked at 122,000 sq. ft. in one
week.
Rinker Materials supplied the concrete with an average of
about 56 truckloads every day between February 2003 and January.
Even so, the project's proximity to FLL's passenger entrance
- and the tight site conditions - meant the contractors were
limited in how many trucks could access the site.
"We'd only have six to eight trucks on site," said
Gillette. "We were lucky. Rinker's facilities are less
than 2 mi. away from here. They delivered a truck every six
minutes."
During the summer months, pours started as early as 4 a.m.,
and later moved to 5:30. The concrete contractor is a joint
venture between Form Works and Baker Concrete. D.L. Kirby
was subcontracted by Form Works/Baker to supply, place and
finish all of the concrete. Kirby subcontracted the concrete
finishing to J & M Contractors. TCOE Corp. furnished and
installed all of the rebar and post-tensioning.
The second-floor slab, which separates the quick-turnaround
area from the rest of the facility, was built to provide a
four-hour separation in case of a fire. To accomplish this,
it has additional structural steel reinforcing, higher-strength
concrete and was specified as a wet cure, with moisture blankets.
Rewriting the Code
The CRCF's unique nature created design and planning complexities.
For example, the project didn't fit neatly into any of the
building types included within the newly revised Florida Building
Code.
"We've had to apply the intent of the code to this building,"
McClendon said. "We've got 126 fuel nozzles, a foam-deluge
system and multiple occupancies in one building. So we've
got a number of code issues that normally don't apply to a
parking garage. In some cases we've had to literally write
the code."
He added that the decisions made for this project may eventually
become the state standard for this type of facility, with
some potential for adoption as a national model.
Spillis Candela DMJM of Coral Gables served as both architect
and engineer for the project.
The decisions for the FLL project mainly related to the CRCF's
first-floor area and the multiple utilities and fire-related
issues there. Installation of the various items required for
this area didn't begin in full until the structural concrete
work had reached the fourth floor.
"We weren't able to put in the underground utilities
until after the structure was up," Gillette said. "That
enabled us to work installing utilities with a lid over our
head. Those subs - which were Fisk Electric, Nagelbush Mechanical,
the Poole & Kent Co. and Phoenix Products - had a tremendous
job to do with working with the structure overhead, with all
of the columns up. Compared to how it's normally done, it
was a tremendous task."
This first floor required a 19-ft. floor-to-floor height
and a 16-ft. clearance at the fire lanes to accommodate any
fire trucks that might need to access the facility.
Six 25,000-gallon fuel tanks are exterior to the facility.
Fueling lines run from these underground tanks to the dispensers
within the building.
Also to the exterior of the building, five 40,000-gallon
tanks measuring approximately 73 ft. long and 10 ft. in diameter
are being installed to gather the material released through
the facility's foam-deluge system.
This system is tied in with other safety characteristics
built into the building, such as a system of five ventilation
shafts - with each shaft having nine fans - that together
comprise a four-hour shaft that runs up from the first floor
to the roof, through the middle of the structure. These nine
fans would only begin running once the foam system was initiated,
and the rest of the building's ventilation system was shut
down.
In late February, the project team was just finalizing the
first floor's utility and concrete slab work.
Much Remains
Bunnell said that even though the structure is topped out,
much remains. Design of the tenant finishes for the 10 or
so rental firms that will be using the facility is still progressing,
with Spillis Candela coordinating with the various companies.
Cummings/Centex-Rooney will build the shell for these tenants,
though each firm is expected to hire its own contractors for
tenant build-out.
Utility work outside the building's footprint has been a
"dance" from the beginning, and remains a focus
of activity, said McClendon.
"We are building an elevated busway right over the utility
corridor, so we have been dancing around force mains and 84-in.
storm drains since we started this project," he said.
The project's overall completion date is December 2005, though
an earlier milestone looms this year.
"The critical completion date to the airport - and the
critical, most difficult one for us - is the lower four floors
have to be complete by Dec. 28, " Bunnell said. "Once
we achieve this the final completion will be a slam dunk."
Project Team:
Owner: Broward County Aviation
Department
Program Manager: URS, Fort Lauderdale
Construction Manager: Cummings/Centex-Rooney,
a joint venture between James A. Cummings Inc., Fort Lauderdale,
and Centex-Rooney Construction Co., Plantation, Fla.
Architect/Engineer: Spillis
Candela DMJM, Coral Gables, Fla.
|