|
Interstate 85 Bypass
Blythe, Barnhill Complete Section
of Emerging Greensboro Urban Loop
Blythe Development and Barnhill Contracting overcame serious
schedule hurdles to complete each of their $55 million contracts
for the new Interstate 85 Bypass in North Carolina. The
two contracts collectively represent an important step in
the construction of the 40-mi. Greensboro Urban Loop.
By Scott Judy
Blythe Development of Charlotte and Barnhill Contracting
of Tarboro, N.C., recently completed a pair of $55 million
contracts for a 15-kilometer section of the new Interstate
85 Bypass in Greensboro, N.C.
The late February opening of the new stretch of highway was
an important development in the progressing 40-mi. Greensboro
Urban Loop project.
The newly opened bypass should make the existing I-85 safer.
It will take an estimated 40,000 to 50,000 vehicles - including
a lot of trucks - away from the "Death Valley" area
where I-85 merges with Interstate 40.
"I've already seen how it's relieved the congestion
through the old section," said Chris Kirkman, resident
construction engineer with the North Carolina Department of
Transportation. "It's amazing just to see the truck volume.
There are a lot of trucks out there now."
The existing I-85 was handling about 120,000 vehicles each
day, he said.
Brad Wall, division construction engineer with NCDOT, said
the opening was a bit early and definitely appreciated.
And Kirkman added, "Both contractors did exceptionally
well to get this section complete and open by February."
Getting to opening day was an arduous journey for the contractors,
though, with both experiencing a significant schedule compression
due to added work and unusually wet conditions that hit during
the paving stages.
"It was something tough," said Drew Johnson, vice
president for Barnhill Contracting's highway division.
Some Unusual Situations
The contracts featured mainline concrete pavements, a fairly
unique situation for the asphalt-dominated North Carolina
highway market. The majority of the two projects was built
eight lanes wide, though a portion of Barnhill's contract
was six lanes. The new road runs around the southern edge
of Greensboro, from an I-85 interchange on the east side of
town back to I-85 on the southwest side of the city.
Across both projects, mainline pavement thickness varied
somewhat between 250 and 330 millimeters, or about 13 in.
This concrete rests on top of a 4- to 5-in. layer of asphalt,
which in turns sits atop a 7- to 8-in.-thick subgrade stabilized
with either cement or lime. Shoulders were a combination of
asphalt and dirt.
Work for both sections started in 1999, with completion dates
scheduled for roughly mid-2004. Blythe's 7.8-kilometer-long
contract - for the west end of the bypass as it connects into
existing I-85 - started first.
Following close behind was Barnhill's 7.4-kilometer project,
which extends from west of Elm-Eugene Street to northeast
of Wylie-Lewis Road, essentially spanning between Blythe's
job and another 2-mi. section of the bypass completed in May
2002.
Both projects included roughly 10 bridges.
In all, there was a total of approximately 500,000 sq. meters
of concrete pavement for the two projects, along with the
approximately 15 kilometers of inside and outside asphalt
shoulders. Unfortunately for such paving-intensive projects,
Mother Nature threw the contractors a curve with an exceptionally
wet 2003 - right on time for all of the paving work.
As the contractors were falling behind schedule - some estimated
it rained about four days a week through September - NCDOT
added work items, such as two additional lanes for the length
of Blythe's contract and some more ramps on Barnhill's job.
Because of the rain delays NCDOT owed both contractors sizable
extensions of time, said Patrick Smith, regional manager for
the Southern division of McCarthy Improvement Co., the concrete
paver for both projects.
Blythe's contract had started earlier than Barnhill's, and
so it was considerably closer to completion. However, to open
up the entire section at once, Barnhill's middle section needed
to be accelerated.
"Barnhill's project had a lot later completion date,"
said Kirkman, estimating the revised schedule to be June.
To expedite the work, NCDOT offered a financial incentive
to Barnhill to get its section completed earlier. Johnson,
the firm's VP, said it mostly involved added manpower and
equipment.
"We put in about five grader crews and four asphalt-paving
crews," he added. "We worked some day and some night,
and pushed it hard. We probably got a year-and-a-half's worth
of work done in about six-and-a-half months."
Johnson credited superintendent Rollin Moye, assistant superintendent
Larry Cliborne and the crews involved. "They were there
sometimes seven days a week to make sure this happened,"
Johnson added. "I commend them a whole lot."
While the contractor wasn't able to fully meet the accelerated
schedule, it came close.
"They didn't achieve the date that was in the agreement,"
Kirkman said. "But they were able to put the resources
on the project and ultimately we got it open earlier because
of this acceleration."
The Concrete
Perhaps even more unusually, the projects were an example
of a nearly bygone era - the highway project built in virgin
area, with no traffic concerns. That helped McCarthy Improvement
speed its concrete-paving work at crunch time and ultimately
succeed at keeping three separate masters - Blythe, Barnhill
and NCDOT - satisfied during a stressful situation.
Going in, the plan was more relaxed.
"We were going to run like a little train, where we'd
have one job pretty close to completing and then we'd just
kind of roll into the next one," McCarthy Improvement's
Smith said.
It didn't work out that way. Instead, "Basically we
were jumping back and forth between the two projects,"
Smith added. "What should have been a reasonable paving
sequence and season basically was compressed. Everything was
forced into a smaller window."
McCarthy couldn't simply add crews or equipment, either,
as every other contractor in the area the firm was working
for was in the same position.
"We were running a little thin last year because every
one of the contractors experienced delays," Smith said.
"We didn't have the luxury of additional crews."
Even so, McCarthy came through. On its best days the concrete
paver placed slightly more than 3,000 cu. yds. of pavement.
The company used a Gomaco 3500 paver and Rex placer/spreader
to pave two lanes wide most of the time.
"It was pretty straightforward paving," Smith
said. "With the new construction, we didn't have to deal
with traffic. That aspect of it was fairly decent."
But speed wasn't everything. NCDOT was focused on the new
road's rideability. The agency had experienced problems with
other recent concrete pavements and wanted to make sure that
didn't happen here. Ultimately, McCarthy was able to meet
the state's rideability specs, a fact Smith attributed to
the firm's use of a placer/spreader to deliver the concrete
to the front of the paver and keep it moving.
"It provided a real nice, smooth ride," Kirkman
said. "The rideability was pretty impressive. They didn't
have a lot of must-grinds. There were some areas, but over
the area that they had to do, it was very impressive."
Despite the project hurdles, Barnhill's Johnson said the
project "turned out fairly well."
The Greensboro Urban Loop project is accelerating now, with
two $100 million-plus contracts progressing. NCDOT expects
the 40-mi. project to complete sometime after 2010.
Project Team:
Owner: North Carolina Department
of Transportation
General Contractor: Blythe
Development, Charlotte
General Contractor: Barnhill
Contracting, Tarboro, N.C.
Concrete Paving Contractor:
McCarthy Improvement Co., Greensboro, N.C.
|