|
Phase 2 of the Carolinas Bay Parkway
APAC at work on $54 million design-build
job for SCDOT
By Debra Wood
Recognizing the immediate need for additional roadway, the
South Carolina Department of Transportation is adding a 30-mi.
long, limited-access highway to serve the Grand Strand area.
"It's another link in the chain of building an overall
impressive and needed project," said Berry Still, program
manager with the SCDOT. "There's a lack of infrastructure
in the Horry County region. The highway is needed to give
relief to the already congested roadways that are out there."
SCDOT awarded APAC Inc. of Atlanta a $54 million design-build
contract for the second phase of the Carolina Bays Parkway,
a 4.6-mi., six-lane road that skirts the beaches.
"Design-build is not only faster. It allows for more
innovation and creativity in the design and construction of
highway projects," said Jim McAleer, vice president of
major projects for APAC. "The efficiencies are potentially
significant."
McAleer said securing the SCDOT contract was important to
APAC because the company had recently put together a major
projects design-build team.
"We had a couple of losses on projects we pursued in
North Carolina, and we did a very thorough critique to determine
what we did wrong and what changes we needed to make,"
he added. "Because [the jobs] require a far amount of
creativity, you have to put the best team together very early."
Engineers LPA Group and Wilbur Smith Associates, both of
South Carolina, and bridge contractor United Contractors of
Chester, S.C., joined APAC in formulating a bid. APAC selected
its partners based on their expertise. The firms began working
together 1.5 years before SCDOT awarded the project in spring
2003.
"One down side of design-build is there are more up-front
costs in pursuing these projects," McAleer said. "For
that reason, you have to be selective in which ones you pursue
and which you don't. Most of the cost is on the design side
because a certain amount of design has to be done so contractors
can price the work."
McAleer said some states offer stipends to partially defray
the cost, but South Carolina did not. APAC currently has 10
design-build projects under way - eight in Florida, one in
Virginia and the Carolina Bays.
SCDOT had already purchased the right-of-way and completed
subsurface testing. The design-build team was required to
meet certain DOT parameters but had enough leeway to propose
several efficiencies.
"We made some alignment changes, minor, but enough to
shorten some of the bridges, and we also lowered the grade
down through the mainline to save money on earthwork,"
said Jim Wiley, APAC's project manager. "Design-build
allows you to be innovative and come up with solutions that
are better than the other participants [who are bidding].
You win the job based on your innovation, not just the lowest
price."
APAC began work on the Carolina Bays project in May 2003
and began construction before designs were finalized. It expects
to complete construction by Dec. 7. Wiley calls it an aggressive
schedule but one he expects to meet.
The company received additional points on its bid for the
speedy schedule. The project was 30 percent complete in February.
The controlled-access road project includes two major interchanges,
with highways 501 and 544, and five concrete bridges with
metal decks. The bridges range in length from 225 ft. to 350
ft.
The road has a cement-treated aggregate base and an asphalt
section topped with an open-graded friction course.
Highway 501 carries significant traffic flow, requiring APAC
to perform much of the work at the intersection at night with
lane changes. United Contractors is handling bridgework and
the mechanically stabilized earth walls.
"We have permanent traffic control in place, and from
time to time, we use temporary traffic control to cross up
and over," said Bill Hedgpath, construction manager and
vice president of United. He estimated that his company will
complete about 10 percent of the bridgework at night.
The majority of the road runs through woods and swamp, but
a portion is adjacent to the Hunter's Ridge subdivision, and
some residents expressed displeasure with building a highway
in their back yards. APAC will add a landscaped berm as a
buffer.
Construction required extensive earthwork. Subcontractor
R.E. Goodson Construction Co. of Darlington, S.C., will move
2.8 million cu. yds. of dirt from highland borrow pits, with
rights purchased from private owners, to build up the road
site. Goodson also cleared the right-of-way, installed pipe
and will plant grass after the road is completed.
"We're doing everything except for the base and asphalt,"
said James Goodson, project manager for R.E. Goodson. The
company expects to wrap up the earth moving by July.
Goodson said phase two of the Carolina Bays Parkway runs
down an old ridge and has had little wetland impact. Sections
of the entire 30-mi.-long road pass through environmentally
sensitive areas and pristine wetlands, so transportation officials
purchased the 12,000-acre Sandy Island, a fresh-water coastal
island, as a mitigation bank.
"The whole mitigation plan was an elaborate group effort
between all the resource agencies, the DOT and local interests,"
Still said. "It actually won a national award for establishing
the bank."
The Sandy Island mitigation won the Federal Conservation
Award in 1997. Mitigation was complete before APAC received
the contract.
About 150 people are working onsite on the phase two project.
There have been no lost-time accidents or environmental issues
as of February.
"The quality of the work is really high," Wiley
said. "It's a good ole' highway job, and certainly one
that will conclude very quickly."
Useful sources:
South Carolina Department of Transportation
http://www.dot.state.sc.us/Projects/CarolinaBays/
|