|
Speeding Along: The Reversible-Lanes
Bridge
Six Miles of Bridges Taking Shape
in Tampa
By Scott Judy
Editor's
Note: This article was written
and published prior to the April 13 event where a sinkhole
opened up directly underneath one of the bridge's piers,
causing two deck spans to collapse to the ground.
The Tampa-Hillsborough County Expressway Authority's intriguing
Reversible-Lanes Bridge project continues to generate national
interest as the contractor building the $143.5 million structure
picks up its pace.
While the owner continues to entertain officials from as
far away as Alaska interested in the project - not to mention
its coverage by several national magazines - PCL Civil Constructors
of Tampa has ramped up its erection of approximately 6 mi.
of precast concrete segmental bridges extending across a 12-mi.
stretch from Brandon to downtown Tampa. In the morning, the
three-lane facility will provide a one-way, non-stop shot
from Brandon to downtown, and in the afternoon it will bring
those same folks home.
Using two separate custom-built under-slung truss systems,
PCL is currently erecting about 64 precast segments per week,
equivalent to roughly 600 ft. of bridge. That's equal to about
four of the 142-ft.-long spans. The pace is somewhat surprising
to PCL, which so far has manufactured approximately 50 percent
of the project's 3,032 total segments, and erected roughly
25 percent of them.
"Right now we're doing a span [per truss] every 2.5
days," said Scott Updegrave, PCL's construction manager.
"We could be a little ahead of schedule."
Patrick McCue, executive director for the expressway authority,
wasn't hedging his bets quite as much.
"They're predicting that if they can maintain their
current rate of construction they'll finish about six months
early," he said. "I think they're actually surprised
at how quickly it goes up."
But it's still far too early to celebrate. With 75 percent
of the erection work remaining, PCL has plenty left to do.
Work began Jan. 12, 2003. The completion date is July 15,
2005.
In all, PCL's contract includes three bridges, one measuring
4,000 ft., another 7,000 ft. and one 17,000 ft.
Speed
The 60-ft.-wide segments will accommodate three 12-ft. traffic
lanes and two 10-ft. shoulders. With its more than 3,000 units,
Updegrave said this is one of the largest segmental bridges
in the country, and one of PCL's largest bridge projects ever.
Case Atlantic of Clearwater is installing the 220 drilled
shafts that will support the bridges' 220 columns. The drilled
shafts are about 70 to 80 ft. long, and 6 ft. in diameter.
PCL has two chain-driven trusses that bear the weight of
the segments until the span is completely erected and the
weight transferred to the piers. Crews then launch the truss
to the next set of columns, usually doing so in 20 to 30 minutes.
"We've put a lot of automation into this under-slung
truss," Updegrave said. "It's like a roller-coaster
chain. The segments sit on some carriages, and this chain
tracks them down the truss and puts them in position. The
carriages have hydraulics on them also. They hydraulically
set the elevation, so all of the segments get together. The
truss itself works off winches. You just turn on the winch
and it launches itself over to the next set of piers."
It took about a month for the contractor to figure out the
process and about 18 days to complete the first span.
Five 14-axle trucks with 140-ft.-long trailers purchased
especially for this project transport the 80-ton segments
from PCL's Port of Tampa casting yard to the jobsite, usually
at night. A 250-ton crane at each truss location then lifts
the segments into place.
Six Lanes in 6 Ft.
By having the facility's three lanes - all built on piers
that are 6-ft. square at the base within existing median space
- functioning in each direction, the authority touts the bridge
as providing "six lanes in 6 ft."
This project innovation was the child of necessity. It was
only because of its limited existing right-of-way along the
Lee Roy Selmon Crosstown Expressway - over which the reversible
bridge rests - that the authority gave thought to a bridge
along the route.
The cost feasibility for such a large project was an obvious
issue, however. Executive Director McCue had worked on the
Sunshine Skyway project and thought a segmental bridge might
be a cost-effective approach. The area's commuter nature brought
forth the concept of a reversible bridge.
Approximately 75 percent of traffic heads toward downtown
in the morning and a similar percentage travels in the opposite
direction in the evening.
Still, the authority's original request for design proposals
only specified a bridge. Only Figg Engineering Group of Tallahassee
proposed a pier-based concrete segmental bridge concept.
"When Figg proposed building this bridge, it made the
biggest impact on the board," McCue said. "Of the
three short-listed companies two proposed building it on earth
walls. The board just didn't like that."
The authority also liked the segmental method's rate of construction
and its minimal impact on traffic - an important consideration
to a toll authority. A pier-based bridge minimized environmental
mitigation costs. It also left the authority with 40 ft. of
remaining right-of-way - enough to eventually accommodate
two more lanes of traffic at grade.
And, "It turned out to be an extremely economical project,"
McCue added. "We've calculated we're building this bridge
for $65 per sq. ft., which is at least $15 per sq. ft. less
than any other major bridge in Florida DOT's bridge database.
So we were really thrilled from that standpoint."
A 100-Year Beauty
The authority wanted the facility to be good looking - and
was willing to pay for it.
"People are deeply resentful of transportation projects
that are functional but ugly," McCue said. "They
blight communities and sometimes divide communities, and it's
really unnecessary. By applying a little more imagination,
you can build a project that's beautiful and really enhances
the community."
With that mindset, "We had to build a landmark,"
he added.
To that end, Figg's design incorporates a curvilinear design
to the bridge segments, varying bridge heights, a two-tone
color scheme and lighting.
Even so, PCL fought the design's aesthetics at first, proposing
to reduce the cost of its contract by an estimated $5 million
to make the bridge more angular. The authority balked at that
and stood firm to the original design.
"We objected to aesthetics per se, because it was more
of a burden," Updegrave admitted. "The geometry
control was a little different. With curves, it's tough to
get the forms to line up. There were air bubbles forming on
some of the curved surfaces, so we had to figure out how to
burp the forms."
The contractor has seen the light, though, and is now an
advocate of the bridge's aesthetics.
"We've figured it out and actually we're glad,"
Updegrave said. "If you're going to build a bridge, why
not build a pretty one?"
The bridge's beauty should prove to be more than just skin
deep. It has been designed and built to last 100 years. Segments
are being built with extra reinforcing steel and 10,000-psi
concrete with an above-average percentage of cement.
"We're really opposed to the idea of short-term projects
that either fail physically or fail functionally in 20 years
or so," McCue said. "The bridges we have on our
expressway today are only 20 years old and they're falling
apart. We vowed we'd never let that happen again."
On this project, he added, "We feel we've got a facility
that will function for 50 to 100 years without changing. It
just made sense to design it structurally to make sure it
held up that long."
Updegrave said he also believes this project will prove to
be a once-in-a-lifetime effort.
"This is my 20th year with the company, and this is
definitely the biggest challenge I've ever had," he added.
"It's not over yet, either. But we're on track."
Project Team:
Owner: Tampa-Hillsborough County
Expressway Authority
Design/Construction Engineering and Inspection: Figg Engineering
Group, Tallahassee
General Contractor: PCL Civil
Constructors, Tampa
Foundation Contractor: Case
Atlantic, Clearwater
Concrete Supplier: Cemex, Tampa
|