|
Another Step Forward for Atlantic
Station
$2 billion development coming alive
with SouthTrust Tower completion
A change in the building's height and a desire to achieve
LEED certification were among the hurdles the construction
team of Hardin Construction and Smallwood Reynolds Stewart
Stewart had to overcome on this first commercial office
building for Atlanta's Atlantic Station.
by Scott Judy
Atlanta's $2 billion Atlantic Station development, billed
as a "live-work-and-play" destination, took another
step toward full realization with the recent completion of
its first commercial structure, SouthTrust Tower.
General contractor Hardin Construction of Atlanta was on
schedule to deliver the 24-story, $40 million core-and-shell
project April 1. Getting to that point involved some fancy
footwork by Hardin and project architect Smallwood Reynolds
Stewart and Stewart of Atlanta, as the parties juggled significant
project changes, including additional floors and a desire
to attain LEED certification.
Getting Started
Hardin started work in December 2002. The project required
three levels of parking underneath the building, and, at the
time, 17 stories above that. Changes came quickly, however.
"As we were coming out of the ground with the foundations,
the owner (Atlantic Station LLC) decided it might be a 20-
or 21-story building," said Skip Loman, construction
manager for Hardin. The construction team redesigned the building's
caisson-based foundation system, adding caissons.
The site was a tough one for the foundation contractor, Long
Foundation of Tarrant, Ala. The contractor encountered steel
slag dumped on the former Atlantic Steel site while drilling
the approximately 30 caissons, which ranged from 10 to 40
ft. in depth.
"If they hit the slag we had to cut the slag out,"
Loman said, adding that this material was then hauled to an
EPA- and city-approved site.
The site wasn't all bad, though. A section of solid bedrock
granite also sat beneath the project. When the contractor
found these sections, caisson depth was minimal and installation
easier.
Still, "Getting the foundations in probably took a month
longer than we had anticipated," Loman said. "The
cost of dealing with the rock was probably twice of what the
original caisson contract was. It was a pretty intensive rock
job."
Even as the structure progressed vertically, the owner made
changes in the building's height.
"By the time we got to the lobby level they were pretty
sure they were going to go at least 20 stories, so we beefed
up the structure in the middle of the building, and then they
added a 22nd floor - all while we were going up," Loman
said. "We were about halfway up the building when they
finally decided how many floors it was going to be."
Brian Leary, vice president of design and development at
Atlantic Station LLC, said the change in the building's height
was a byproduct of the development's popularity.
"Increasing the building's height during construction
is a good problem to have," Leary added. "It says
that the demand for an Atlantic Station address was greater
than even we expected."
With the new height, the building now needed more elevators
- a trick considering the core was already designed.
"We had to get two more elevators into the building,
within the same sized core," Loman said. "We were
able to sneak an extra elevator in the two high-rise banks
without actually changing the core."
Accelerating
As the project moved forward, the team continued to feel
the impact on the schedule of both the initial delay with
foundation work and the building's expansion upward. Though
the project had grown in scope, the original 16-month schedule
remained fixed.
To make up time, Hardin worked with formwork contractor Southern
Pan Services of Lithonia, Ga., and other subs to speed the
structural concrete stage to a rate of one floor every five
days. Mostly, Loman said, "It was just a lot of overtime."
There was actually more to it than that. The concrete contractors
used a concrete mix that would reach specified strengths within
24 hours, and then staged crews through roughly 15-hour days.
"We would start a pour at 2 a.m. and by 7 a.m. the finishers
were leaving the site," Loman said. "By 8 or 9 a.m.
they had the control lines popped and the columns [contractors]
were on the slab by noon and were pouring columns by 3 or
4 in the afternoon.
"They were stressing cables the next morning and dropping
tables. So 24 hours after they poured on it, they were stressing
cables and dropping them."
This was the scenario for all floors above the first two.
These typical floors measured 13 ft. 4 in. floor-to-floor
and were built with two pours per floor.
Other concrete contractors included AmeriSteel of Duluth,
Ga., reinforcing steel; Precision Concrete of Alpharetta,
Ga., placing and finishing; and DSI of Tucker, Ga., post-tension
cables. The project topped out Sept. 25.
Outside, Inside
Curtain wall comprised of a combination of metal panels and
granite makes up the exterior of the building. Subcontractor
JAMCO, Marietta, Ga., handled the erection of the curtain
wall system and installed the granite into it. This part of
the project "went better than planned, better than scheduled,"
Loman said.
A two-story screen wall encircles a portion of the roof's
perimeter, adding to the building's perceived height. The
screen wall system is illuminated from within.
Interior work is relatively limited. Hardin and its subcontractors
are finishing out six floors for SouthTrust Bank, and other
contractors will complete interiors on eight others.
Here, though, the owner threw the construction team another,
final curve - the desire to go for LEED certification.
"We got word they wanted to go LEED about halfway up
the structure," Loman said. Still, the timing wasn't
too bad, just prior to getting final documents for the interiors.
Also, because it's a core-and-shell project, interior work
wasn't too extensive.
"The core-and-shell materials is not a whole lot,"
he added. "It's mainly the main lobby." For this
reason, the building will likely earn the indoor air quality
credit.
"The lobby is primarily either marble or granite,"
Loman said. "You don't really have the high-VOC paints
and caulks, as most of it is hard-surface materials. And we're
using low-VOC paints and adhesives and caulks."
He said a major reason the project had a chance at attaining
this certification in the first place was that it is part
of a brownfield redevelopment, which is what Atlantic Station
is considered.
Another factor in favor of achieving LEED was Atlantic Station's
use of a central chiller plant for the entire development,
meaning the SouthTrust building doesn't have a chiller, and
all air-conditioning units are CFC-free.
The building is expected to earn points for the use of local
materials and recycling because of the curtain wall is made
up of recycled aluminum.
The commitment to LEED certification was important to the
owner.
"It started with the site remediation and clean-up of
the former industrial facility, continued with the installation
of [the] sanitary and stormwater system, set a national precedent
through a partnership for Smart Growth and air quality improvement
with the U.S. Environmental Protection Agency and took the
next logical step with the commitment to 'green' building
construction," Leary said.
"Too much of what is built today is fully a function
of a short-term proforma that gives no value to sustainable
measures that not only positively affect the built environment
on day one but pay back not only the building owner but the
community as well over time," Leary added. "Instead
of adding 3-5 percent to the capital cost of a building we
are able to reduce that closer to 1 percent and then recover
that cost through the more efficient operation of the building."
Hardin's Loman is pleased with the end results.
"I'm going to be real proud come April 1 when we turn
it over," he said in February. "It's a really neat
deal for this whole development and Atlanta. They've been
talking about it, and it's becoming a reality."
Key Players:
Owner: Atlantic Station
LLC, Atlanta
General Contractor: Hardin
Construction Co., Atlanta.
Architect: Smallwood Reynolds
Stewart Stewart & Associates, Atlanta
|