|
Hartsfield Runway Spans Interstate
Hartsfield-Jackson Atlanta International
Airport's new 9,000-ft.-long 1/28 runway is part of the airport's
$5.4 billion expansion plan.
by Victoria L. Tanner
Scarlett O'Hara and Rhett Butler have long reigned as Atlanta's
brashest couple, but once Kathryn Masters and David Casey
finish the ambitious construction project they're leading
at Hartsfield-Jackson Atlanta International Airport, O'Hara's
and Butler's title may well be gone with the wind.
Masters and Casey are involved in building a critical component
of Hartsfield's new 9,000-ft-long 10/28 runway, the centerpiece
of a $5.4-billion airport expansion. Their massive $159.5-million
bridge structure will permit the runway to cross over Interstate
285, allowing planes to take off and land literally atop the
busy road.
The bridge configuration is believed to be unique. It will
span 10 lanes of traffic but allow for eventual expansion
of the road up to 18 lanes. The bridge is so vast that the
support structure will create a tunnel, although none of it
is underground. The structure will be the first roadway tunnel
in Georgia.
"When I first took over the project and they told me
it was design-build, I thought it was going to be a disaster,"
said Masters, senior project manager for International Aviation
Consultants, the joint venture providing program management
services to the City of Atlanta and its Department of Aviation
for the five-year expansion project. "The city has never
done a design-build like this," Masters said. The project's
intense schedule made design-build a logical choice, although
she acknowledges that city officials have "found it very
difficult to give up control" under the design-build
paradigm. IAC is comprised of Parsons Aviation, Rosser International,
H.J. Russell, Turner Associates and URS Corp.
Masters knew that the project's proximity to state roadways
also would require a close working relationship with the Georgia
Department of Transportation, another agency with limited
knowledge of design-build project delivery. "I've always
thought this job was like having two novice owners,"
said Masters. She worried that GDOT's internal structure was
not well suited to the demands of the job's fast-track schedule,
fears that so far have not materialized. Since the job's kickoff
in early 2003, the team and the project have come together
quickly. "It's gone very well so far," said Masters.
"We're on schedule and on budget."
For the design-build team, juggling tight schedules and budgets
is just part of the process. But coping with the unique design
and engineering demands of the project raises the stakes considerably.
The structure incorporates a main runway bridge that measures
1200 ft long and 486 ft wide, and a 450-ft-long, 450-ft-wide
taxiway bridge. Casey, program manager for Archer Western
Contractors Ltd., Atlanta, leads the design-build team. The
Atlanta office of Parsons Brinckerhoff Quade and Douglas Inc.
is the team's lead design engineer, while Heath & Lineback
Engineers, Marietta, Ga., is handling the project's structural
design.
|
The design-build team did extensive preliminary engineering
work as part of a 15-month pre-bid process in which the city
conducted workshops for potential bidders to learn about the
job and exchange ideas and information as the request for
proposals was being developed. "I think a lot of good
things came out of that process," said Casey. "The
city looked for everyone to bring out the things that were
going to cause significant issues later on." Masters
said the process allowed bidders to "ask questions without
giving away the farm."
The pre-bid process also gave the design-build team the opportunity
to study the minutiae of the city's preliminary plans. "The
hardest part in the pre-bid process was determining what would
and would not be accepted as being responsive to the RFP,"
said Gary Lineback, senior structural engineer at Heath &
Lineback Engineers.
The RFP featured a 35 percent design concept developed under
a separate city contract. The preliminary designs were used
primarily to familiarize various agency groups with the overall
concept for the bridge, thus helping to pave the way for the
design-build process as it moved forward. Specifics of the
drawings were not expressly written into the RFP "because
we felt there was no need to be so dictatorial," Masters
said. However, the city did have "eight non-negotiable
items," including essential criteria like the number
of lanes of traffic to be accommodated. Beyond that, bidders
were given a wide berth in preparing their proposals. "The
RFP allowed for quite a bit of innovation," said Archer
Western project manager A. Steven Hausler Jr. "And we
went for it."
Load Limit
Lineback shouldered considerable technical burden. The load
standard for the entire runway was set at 1.4 million lb.
The bridge was required to handle loads created by aircraft,
such as the Boeing 747 (at 1.04 million lb) and the Airbus
A380 (at 1.33 million lb). Variations in aircraft wheel configuration
also had to be factored into the design equation, as well
as the impact and influence of loads and force created by
shear.
Given the set of variables, Lineback realized that his design
would require a unique solution. "I don't know of any
place in the world to have a project like this that is as
big or as high," he said. Lineback's design features
764 "T-shaped" precast concrete beams with a total
length of 90,000 ft. The beams are 81 in. tall and vary in
length from 94 to 133 ft for both the runway and taxiway bridges.
The combined bridge decks total 725,000 sq ft and will contain
approximately 37,000 cu yd of concrete. The bridge structure
consists of 430,000 sq ft of cast-in-place and precast walls.
The runway's interior substructure features solid concrete
walls measuring 3.25 ft in thickness and varying in height
from 35 to 60 ft.
Given the nature of the tunnel structure, the Archer Western
team knew that the life-safety systems required for the project
would be a major cost component. Turning to the design expertise
of Parsons Brinckerhoff, the team undertook a comprehensive
ventilation study to determine the best methods for complying
with code. "Going into the bid, we were looking at ways
we could make the biggest impact with innovative design,"
said John Durand, PB project manager. "We did extensive
computer analysis, with real-time models of the ventilation
and we modeled the evacuation of people in there as well."
Based on the study's findings, the team developed its proposal
around a dramatic decision to eliminate a conceptual false
ceiling that was in the plans. "It was in the RFP with
a note that it was there for ventilation purposes only and
in our ventilation analysis we decided it wasn't needed,"
Casey explains. The Archer Western team's proposal provided
the city with documentation supporting its argument. "We
saw eliminating the ceiling as a very good opportunity to
save money so we attacked that pretty heavily. We were able
to reduce the number of fans that were placed in the tunnel
to forcibly evacuate smoke by utilizing that ceiling space,"
said Durand. The resulting design features a life-safety system
that includes 10 jet fans, 12 egress doors, emergency power
generation, 4,968 light fixtures, 120 carbon monoxide detection
monitors, a fire protection system and video monitoring. Casey
acknowledges that the extensive pre-bid design work came with
a high price tag. "The risk is so much higher, with no
chance to recoup those costs," he said.
The city prequalified five firms to participate in the two-part,
technical and price, bid process. Once it reviewed the technical
proposals and deemed them responsive to the RFP, bids were
opened and the award was made to the low bidder. Only two
teams submitted final bids and the award created considerable
controversy.
Landmark
The Archer Western bid was approximately $20 million below
a bid submitted by 5R Constructors LLC, Atlanta, a partnership
of S.W. Matthews, APAC Georgia and Michael Thrasher Trucking.
5R Constructors already is working at the airport with a $350-million
earth-moving contract that involves transporting 27 million
cu yd of earth to the runway site. After losing the bid, 5R
Constructors filed suit in federal court, seeking a temporary
restraining order to stop work. It claimed that the winning
bid was not responsive to the RFP. U.S. District Court Judge
Owen Forrester denied the request and cleared the way for
the city to ink its deal with Archer Western in early December
2002. No further legal action is planned, said George Wenick,
an attorney with the Atlanta law firm of Smith, Currie &
Hancock LLP, which represented 5R Constructors.
The Archer Western team credits its advance work in the engineering
design for giving them the winning edge. "I would say
our team out-engineered the other team in many ways,"
said Durand. "One of them was ventilation, one of them
was the innovative superstructure design, and then there were
a lot of smaller items." Besides besting 5R's numbers,
the winning bid was $80 million below the city's initial estimate
for the project.
But perhaps more importantly, the extensive advance design
work allowed the Archer Western team to hit the ground running
once the contract was awarded. Durand estimates that under
a traditional design-bid-build approach, the tunnel's life-safety
systems alone would have required approximately two years
of design work. The design-build approach brought the project
to 95 percent design completion in approximately seven months.
With design nearly complete, Archer Western's construction
team, which is self-performing approximately 55 percent of
the construction work, now bears the burden of maintaining
the project's accelerated pace. Completion is scheduled for
February 2006, with commissioning set for May 2006. Casey
said his team is up to the challenge. "This is going
to be a landmark project in this city," he said. "Everybody's
going to see it and we all want to make sure that everyone
knows that it was a quality project that all of us worked
together to achieve."
With the busy jobsite humming behind them and 10 lanes of
traffic rushing past, Masters and Casey survey the work with
an unmistakably proprietary air. They know it just might be
one of the highlights of their relatively young careers and
they're clearly proud of what they are achieving. "After
this job, there's not much more you could hope for,"
said Masters.
Reprinted from Design-Build, copyright
the McGraw-Hill Companies Inc., December 2003. All rights
reserved.
Key Players:
Owner: City of Atlanta's
Department of Aviation
Program Manager: International
Aviation Consultants, a joint venture of Parsons Aviation,
Rosser International, H.J. Russell, Turner Associates and
URS Corp.
Contractor: Archer-Western
Contractors, Atlanta
Design Engineer: Parsons
Brinckerhoff Quade and Douglas, Atlanta
Structural Engineer: Heath
& Lineback Engineers, Marietta, Ga.
|