|
A New Market for Suitt?
Suitt Construction Design-Building
Its First Federal Project at Pope AFB
Suitt Construction was a pioneer in the development of
the design-build process and is now using its skills in
that area to tackle its first federal contract: a $14-million
corrosion-control facility for C-130 cargo planes at Pope
Air Force Base.
by Bea Quirk
Greenville, S.C.-based Suitt Construction Co.'s ability to
move into new areas to adjust to changing market conditions
is apparent in one of its latest projects: a $14 million corrosion-control
facility for C-130 cargo planes at Pope Air Fore Base in Fayetteville,
N.C.
It is the company's first federal contract and the first
hangar facility it has built. And as it has in more than half
its projects, the firm is using the design-build process.
Suitt is a national leader in design-build and was a founding
member of the Design-Build Institute of America.
Suitt has always outsources design on its projects, and for
the corrosion-control facility it chose BRPH of Melbourne,
Fla., for all engineering and design work.
Kenny Anderson, Suitt's project manager for the Pope facility,
said the firm went after a federal contract because "after
Sept. 11, and with the economy the way it is, you can't be
choosey about the work. The federal government does a lot
of work all over the place. It's a tremendous market we haven't
tapped into."
Even before it was officially awarded the contract, Suitt
had to deal with the differences between working in the private
sector and for the federal government. For example, the bidding
process was in two phases - the first one a selection process
to determine who was qualified, and the second, the actual
bid.
Also, Anderson said that a bid is about 30-40 pages long,
but the one for the Pope hangar filled six spiral-bound notebooks.
"It's a big upfront expense when you bid on a government
job," he added. "It's a time- and labor-intensive
process, and if you don't get the job, you're out the money
you invested."
The design process was also intense and time-consuming. Once
Suitt was awarded the contract on Dec. 9, 2002, it and engineers
from BRPH had 60 days to complete 60 percent of the design
work. The U.S. Army Corps of Engineers, the owner, took 30
days to review the plan and comment. Then Suitt and BRPH had
another 60 days to finish the design.
The Corps then reviewed it for another 30 days, the designers
had 15 days to tweak it and then the Corps got back to them
in another five before the final details were approved. BRPH
engineers remain involved as construction continues.
But Suitt was able to get a head start on the construction
by getting sitework design approved after the first 60 days.
Construction began April 9, 2003, with an expected completion
date in June.
Anderson said the military has its own way of doing things,
and, "We had some growing pains learning how the military
works."
For example, on a typical job, if work needs to be done somewhere,
crew members just pick up their tools and go where they are
needed. On a military base, work crews must get permission
first, a process that takes about two weeks. And when a work
area is located in a restricted zone, workers have to be escorted
by military personnel at all times.
Anderson visits the site about twice a week, and Suitt has
about a dozen staffers onsite. The work crew is made up of
about 70. The Corps has a quality-assurance supervisor in
the field every day, and the Corps' project engineer, Sayed
Hossien Kamalbake, also visits the site once or twice a week.
Kamalbake said the Corps often uses the design-build approach
because it facilitates the faster resolution of problems and
keeps projects on a fast-track schedule.
Pope AFB is part of Fort Bragg, an Army base from where soldiers
and supplies are shipped out to wherever there is a need.
The C-130 is large transport aircraft used for such purposes.
The 68,000-sq.-ft. corrosion-control facility is a conventional
steel building with insulated metal siding. It has 50-ft.-high
ceilings and is made up of two hangar bays - one for washing
the C-130s and one for painting them with a chemical that
helps prevent corrosion.
The need to precisely control air flow in the paint bay is
extremely important. It requires careful design, as well as
perfect placement and alignment of its doors - six of them,
each 5 ft. thick, 26 ft. wide and 40 ft. high - fans, slots,
dampers, filters and valves.
"If the air flow is too slow, it won't take the toxic
fumes out of the building," Anderson said "But if
it's too fast, the paint won't stick to the plane. The flow
must be straight and direct all over the aircraft, without
any turbulence, eddies or pools. It's a matter of controlling
both velocity and volume."
To paint the planes, workers stand on scaffolding and use
spray guns to cover the planes with the corrosion-hindering
chemical. Toxic fumes must be released through vents in the
roof.
Before the building is delivered, engineers will simulate
the painting process and monitor the air flow with special
sensors to make sure the specifications are met.
A waste treatment system must be in place so runoff can be
treated before being discharged.
Anderson said "this project is a gage" to help
his firm decide" if it will pursue other federal projects
in the future. "We will look for the right job and be
selective in the projects we go after."
|