|
Changing the Hidden Landscape
$130 million TIA security enhancements
project is first of its kind in nation
At Tampa International Airport, Skanska USA Building is
leading a nationally unique design-build effort to install
an inline baggage screening system and security enhancements.
The project is at the forefront of a nationwide trend toward
baggage and security systems that are out of sight to airline
passengers, more technologically advanced and give the flying
public a travel experience similar to that of pre-9/11.
by Scott Judy
Deep inside Tampa International Airport, mostly hidden from
view, Skanska USA Building's Atlanta-based Aviation Group
is transforming both the airport's fundamental operation and
passenger experience.
The Hillsborough County Aviation Authority's use of design-build
for its $130 million Outbound Baggage and Security Enhancements
contract is considered the first time ever that a project
of this type has been delivered by this method.
"Nobody else has done any design-build of a baggage-sortation/security
project," said Jim Clemens, vice president with Skanska
and the contractor's project director for the Tampa contract.
"We dreamed all this up. There are five or six other
facilities that have inline systems working, but none of them
are as large or as complex as this."
Rud Mueller, director of architecture for project owner HCAA,
concurred.
"There are installations of these inline baggage systems
at other airports, but of the top 25 airports in the country,
I believe we're going to be the only airport that's going
to be 100 percent inline baggage screening," he said.
The project will provide TIA with high-speed conveyance of
checked baggage incorporated with an inline explosives-detection
system or EDS. Tagged bags will be computer monitored throughout
their trip from check-in until placement on the plane. And
while the new baggage system is the main focus, "We're
not just throwing a conveyor up in the air," Clemens
said.
Skanska's contract also includes a 20,000-sq.-ft. addition
to the new Airside E terminal to accommodate baggage sortation
for carriers flying from Terminal D, as well as the construction
of two new baggage-sorting facilities located next to Airsides
A and F. The first of these, a $16.8 million building called
A Sort, measured roughly 55,000 sq. ft. and was built in 17
weeks. The second, about 35,000 sq. ft., was scheduled for
substantial completion by May. At the conclusion of this phase,
100 percent of all bags leaving Tampa will go through inline
EDS and all ticket lobby screening will be removed.
A Complex Project
Work started in September 2002 and is scheduled to conclude
in March 2005 when Beck of Tampa completes its design-building
of a new Airside C terminal that will be used mostly by Southwest
Airlines. The baggage system Skanska is building will tie
into the new Airside C. When this segment is functional, it
will mark the end of the $130 million contract.
Though the new structures are airside, the most important
activity takes place underneath the landside terminal. That's
where Skanska and its extensive team of subcontractors are
tying new conveyors into existing systems and helping get
the 24 new EDS machines up and running.
The screened bags are "clean" by the time they
leave the main terminal and head to the airside facilities,
but it's a long and sometimes strange trip through TIA's complex
system.
The layout of TIA with a small central terminal and a hub-and-spoke
design of airside terminals presented a challenge to the baggage
system design. To provide a system that screened all bags,
a modular design with screening loops was developed allowing
for groups of EDS modules to address the needed capacity of
the system. It also enabled the system to fit under the landside
terminal between the passenger baggage pickup lobbies.
The system therefore requires complicated computer logic
systems and is "dramatically more difficult from a design
and operation standpoint," Clemens said.
Jeff Clemens, Jim's brother, serves as Skanska's systems
manager and oversees every detail related to the installation
of the new baggage-screening system.
"Because of all of the PLC programming, the timing issues,
and making sure the system works properly, this has got to
be one of the most challenging [baggage-screening] projects,"
he said.
Deep Into the Culture
Overcoming the complexities of the system's design has required
a thorough understanding of the carriers' requirements, expectations
and operations. Process engineers and others on the design-build
team examine every aspect of each airline's operations, and
even suggest better ways of doing things.
Jeff said this involvement is a "handy thing for the
airlines, because they're looking for answers to all kinds
of different things, and we can provide them with those answers.
And a lot of times it betters their operation."
Jim added that the process engineers "look at everything
- whether they (airlines) should be checking in people in
a line here, or whether they should put the international
flights over there. That's the kind of stuff we have to do
all the time in order to be able to control the inputs to
these systems."
Of course, making all of these changes from the old to new
conveyors systems without disrupting the operations is as
critical as can be. "We can't shut them down ever,"
Clemens said.
To that end, Skanska first must make sure that every superintendent
and every subcontractor understands exactly when and where
changeovers are to occur, and coordinate closely with airline
representatives and airport authorities.
This type of direct and intimate involvement with the operations
of a facility as complex as a major U.S. airport makes this
project different from most, added Clemens.
"We have to be constantly on watch that whatever actions
we're taking are not causing negative reactions to the operational
availability of this airport," he said. "We have
to have supervision available 24 hours a day, seven days a
week, because if a belt brakes or a roller bearing fails,
if there's a software issue or whatever, we have to be on
top of that within seconds.
"And if we can't make a fix to the mechanics or the
electrical aspects of the hardware, we have to go into contingency
plans to bring additional resources to the project and move
baggage by hand if we have to. There's no way we can stop
the progress of this baggage, or else you're going to have
jets sitting on the runway."
Design-Build
Essentially the project boils down to its design-build nature.
From its first-in-the-nation status to the interactive suggestions
to the airlines, everyone agrees design-build makes it all
possible.
"Design-build is a huge part of the equation because
it allows us to not have the year or whatever to plan and
then get to the task at hand," said Lou Russo, HCAA's
senior director of planning and development. "We were
immediately able to respond and start to make those changes."
Design changes were easier than in traditional delivery methods,
said HCAA's Mueller.
"With all of the revisions that have come down this
year, it would have been much more difficult with a separate
designer and constructor to accommodate those changes if you
were working in the traditional manner," he added. "Having
a design-builder that's responsible for the entire delivery
of the project has really benefited us because we've been
able to make revisions and modifications ongoing, as opposed
to having them first designed, then provided to a contractor,
priced, negotiated and then authorized."
Jim Clemens is a design-build disciple who's turned into
a missionary.
"We've got to get the story out," he said. "We've
got to tell [owners] that, 'If you've got a hard project;
if you've got a tight budget, if you want to save money and
do it fast - faster than you ever thought you could do it
- you need to go with design-build."
Getting subcontractors to understand their responsibilities
under the design-build method - including bidding a complex
project based on incomplete design documents - has been a
major focus for Skanska.
"They are given a very solid understanding of what design-build
means to Skanska and our team here," Clemens said. "We
actually have contract language that indicates that they have
responsibilities for identifying things that may not yet be
totally defined in their design packages."
Therein lies the trick.
"It's a difficult thing to take a 60-70 percent developed
set of drawings, give them to a subcontractor community and
say, 'I want some good, solid, hard pricing,'" Clemens
added. "So there's a lot of back-and-forth between the
superintendents, the project manager and the subcontractor
at bid time to make sure there's a full grasp of what the
scope is, and that minor scope development is not scope creep.
You have to create that mindset with everyone."
Of course, the owner's mindset is the most important one.
So far, it remains positive.
"Overall it's been a pretty pleasurable experience,"
Russo said. "There are so many personalities involved
in trying to make everyone happy. It's certainly a task that
is hard to accomplish. We're very satisfied with how they've
handled that and their coordination efforts."
Key Players:
Owner: Hillsborough County
Aviation Authority, Tampa
Contractor: Skanska USA
Building, Aviation Group, Atlanta
|