|
A New Home for UF's Sports Medicine
Turner Construction is building
the $25 million facility in Gainesville
by Scott Judy
In Engineering News-Record's most recently published Top
400 Contractors Sourcebook, Turner Construction Co. ranked
as the nation's second-largest education contractor, reporting
more than $700 million of work in this sector.
Turner's operations in the southeastern United States are
surely major contributors to its national education total.
Some of the jobs include a $31 million contract to build
a College of Law for Florida A&M University in Orlando;
a $23 million student-housing project at the University of
South Florida in Tampa; a $42 million Pediatric Building at
Atlanta's Emory University; and a $15 million library for
the University of North Florida in Jacksonville.
At the University of Florida in Gainesville, Turner is following
up a high-profile, $50 million expansion of the school's Ben
Hill Griffin Stadium with a design-build effort to construct
UF's new Orthopedics Surgery and Sports Medicine Institute.
The $25 million, 120,000-sq.-ft., four-story facility will
consolidate current clinic, rehabilitation and radiology functions
of the College of Medicine's Department of Orthopedics that
have previously been spread across various other campus and
off-campus locations.
Patients will include student athletes and people with cancer
and those suffering from orthopedic-related injuries.
"You have the surgeons, the rehab, the radiology, the
anesthesia and whatever is necessary to perform an orthopedic
function gathered together in one location," said Miles
Albertson, UF's associate director for facilities planning
and construction.
Design-Build
The project has proceeded under a modified design-build delivery,
with Turner partnering with URS Corp. of Tampa as designer.
The owner chose the Turner/URS team as a result of qualifications-based
interviews.
As an owner, Albertson said the modified design-build delivery
system has proven beneficial.
"Rather than having two sources of responsibility, with
me trying to take documents from a designer and giving them
to the CM - with me essentially being the middleman - the
designer, URS, is working for Turner," he said. "So
if there are any errors in the design, Turner is responsible
for that, versus the University of Florida. It presents a
different contractual arrangement, and one that I really like."
Design work began approximately in March 2002. Albertson
said the first design, for a one- or two-story, nontraditional
structure, was unacceptable to the university.
"The university has certain architectural guidelines
for our campus buildings, depending upon where they fall on
campus," he said. "We lean towards collegiate Gothic
architecture, with Gainesville red range brick and commander
clay-tile roofs. The original proposal that URS came up with
was something that was a radical departure from that, and
the administration insisted that we adhere to the collegiate
Gothic style of architecture."
The initial design's low height was another problem.
"From a real-estate standpoint, we have boundaries and
it's consequently to our advantage to utilize that real estate
as efficiently as possible," Albertson added. "We
don't build any one-story buildings anymore. We try to make
everything a minimum of four stories, and more where practical."
Design Continues
Turner, URS and UF worked on design for about a year, said
Bill Morthland, vice president of Turner's education division
in Orlando.
"The challenge on any project is getting the most efficient
building design from a net to gross square footage standpoint,
which holds the overall cost in control," he said. "We
spent a lot of time looking at massing options that we felt
would improve the efficiency of the building - going more
vertical versus horizontal. The whole key was to drive as
much building program into the budget."
Accommodating the needs of the various end users was a complex
process, Albertson said.
"There were a lot of different owner/users that needed
input into the design," he added. "The coordination
of that took a little longer than normal. Turner and URS did
a great job of making sure that everybody got their input
and [guided them] to get that input onto the paper. It was
a difficult process, but in the end it's worthwhile."
Morthland said this extensive review process was beneficial.
"By the time you make it through the multiple reviews,
everybody gets their input and it promotes getting the scope
into the project so we can estimate and design it," he
added.
Construction Starts
While design was still progressing, the team released a site
foundation bid package to jump start construction. Work began
in March 2003, with substantial completion set for July 2004.
A foundation built of cylindrical steel pipe piles was chosen,
based on geotechnical studies of the site. "We studied
a variety of deep-piling foundations and found that the steel
pile was the most economical," Morthland said. "Some
of the piles extend more than 100 ft.
Gulf Foundation, Tampa, handled this work.
Partly to speed construction, the designer opted for a structural-steel
frame with a composite floor system. Overall building design
was still progressing when the structural-steel package was
released. Allstate Steel Co., Jacksonville, Fla., won the
contract to fabricate the material and Garrison Steel, Birmingham,
Ala., erected it.
"The steel frame is obviously a choice that has an advantage
relative to speed," Morthland said. He added that erection
of the roof trusses was also paced as quickly as possible,
with the systems partially fabricated offsite and then ganged
together on the ground for speedy lifting into place.
"They're built up into modules that might be 30 ft.
long by the width of the building - whatever the crane can
handle - and the whole thing is craned up and dropped on top
of the building," Morthland said. "That helped speed
things up."
Midterm Grades
The project was about 65 percent complete in mid-January
and was on target for its July completion.
"It has all pretty well come off as planned," Morthland
said. "The owner was able to fund some additional build-out
of the third and fourth floors, and we were able to work that
into the schedule, so it's all synched in with what we're
doing."
Albertson isn't going to offer a final grade just yet, but
likes what he's seen so far.
"I give them high marks on everything they've done so
far," he said of the Turner-URS team. "We do a semiannual
evaluation of both the designers and construction managers,
and they've gotten consistently high marks."
He added that the internal workings of Turner - who Albertson
sees mainly as a construction manager - are the major factor
in keeping the project moving forward.
"Their internal structure for managing projects - although
the rigidity of it occasionally is a stumbling block - keeps
things moving all the time and forces you to make decisions
to keep them moving," Albertson said. "That is probably
their strongest point."
Project Team:
Owner: University of Florida
Campus Planning, Gainesville
Contractor: Turner Construction
Co., Orlando
Architect: URS Corp., Tampa
Foundation Contractor: Gulf
Foundation, Tampa
Useful sources:
http://www.ufortho.ufl.edu/department/
|