|
UGA's CCRC
New delivery system enabled timely
completion of UGA project
by Scott Judy
Brasfield & Gorrie's Kennesaw, Ga., office led the recent
construction of the $29 million Complex Carbohydrates Research
Center, a world-class research facility at the University
of Georgia's Athens campus.
The approximately 120,000-sq.-ft. CCRC building features
state-of-the-art equipment and will take its place as one
of the premier centers in the world for the study of carbohydrates.
"In terms of biology, the study of carbohydrates is
the next big area," said Alan Darvill, CCRC director.
"The building of this facility has given us a world-class
research building that gives us space to recruit and attract
world-class scientists to Georgia. It also gives us the space
to house high-tech equipment we need to study the structures
and functions of carbohydrates."
With the project's successful completion two months ahead
of schedule - substantial completion occurred Sept. 29 instead
of late November - the CCRC also has proven to be an important
one for the UGA Real Estate Foundation, the project's developer.
It was the first project of over $10 million that the foundation
has tackled, and it stands as a showcase for the group's nontraditional
approach.
In addition to securing financing - and eliminating any disruptions
that can occur in a political, year-to-year funding situation
- the major difference in the foundation's delivery method
is its ability to impose liquidated damages for late completion
and also to provide early-completion bonuses.
"We are able to do that, simply because we are a private
foundation," said Krista Coleman-Silver, the foundation's
project manager. "We have the freedom to write the contracts
in a way that puts some of the onus on the contractor. It's
just a different delivery system."
The foundation's projects will typically be limited to revenue-generating
facilities, such as research centers that attract grant funding,
or dormitory buildings. Classroom and administration projects
will remain the responsibility of the university.
For this project, Carter & Associates, Atlanta, served
as the program manager. O'Neal Inc. of Atlanta was the project
architect.
The Assignment
Construction began June 1, 2002, with the original completion
date set for Nov. 29, 2003. However, an earlier date of July
29 loomed for completing a connected structure that will house
a world-class neuro-magnetic resonance machine, itself valued
at roughly $7 million. Having an appropriate housing facility
for the NMR, considered the most powerful in the world, was
necessary for CCRC to receive a particular grant from the
National Institutes of Health and was the driving force for
this project.
Because of this timetable, the section housing the NMR would
start first. The contractor then progressed directly onto
the roughly 300-ft.-long, 50-ft. wide, three-story concrete
lab building, which is made up of spread footings, slab-on-grade,
three floors of columns and three pan slabs and a structural
steel roof. The NMR building is structural steel frame with
block walls.
Because the NMR required that only a certain amount of ferrous
material be included within a roughly 30- to 40-ft. radius,
the building had to be oversized.
"We had to build it with enough room that the bulk of
the steel was outside of the magnetic field of the magnet,"
said David Pritchett, project manager for Brasfield &
Gorrie. "The magnet is 15 or 20 ft. tall, and the actual
building is about 45 ft. tall in order to get all of the steel
in the roof high enough to not affect the magnetic field.
The building is about twice as tall as it would normally be."
The slab in this building features fiberglass rebar in order
to reduce the amount of ferrous material, and landscaping
outside the structure utilized hollies and other bushes that
would prevent people from getting too close.
During this past summer, however, CCRC officials notified
Brasfield & Gorrie that the delivery of the new NMR would
be delayed, thereby canceling the need for the structure's
early completion. The construction team then used it for storage
for a period of time.
When delivered, the approximately 19-ton NMR will be sent
in through a pair of 17- by-17-ft., bolted-down, structural-steel
hatches in the roof and ceiling.
A red brick exterior and shingle roof is in keeping with
the university style.
Keeping People Happy
Brasfield & Gorrie and the rest of the construction team
had to keep two sets of people happy - those who would be
using the building and everybody else.
For the users, Brasfield & Gorrie's management team worked
most closely with Carl Bergmann, an associate research biochemist
and CCRC's project manager. Bergmann's full-time job essentially
switched to overseeing this project, a necessity because of
its complexities.
"Very early on it became obvious we would need a scientist
involved in order to get the building set up to do what we
wanted it to do," Bergmann said. With the vast majority
of the building dedicated to labs, each run by individual
researchers, Bergmann's main job was communicating the very
specific requirements of each researcher to the contractors
and designers.
"My job was to be as clear and as explicit as I can
be as to how we need the building to function," he said,
adding that the scientists had very specific preferences and
know what works well and what doesn't.
Pritchett said this part of the project was the most difficult.
"The most demanding [part] was the coordination of the
lab requirements - getting all of the piping and equipment
necessary for all of the lab equipment in the building,"
he added. "Probably 90 percent of the building is labs,
and all of those areas are full of lab casework, lab gas,
fume hoods, acid-waste systems, vacuum systems and lab gas
systems. With three or four [sub]contractors working on each
lab, the coordination between the building systems and the
lab systems was probably the most difficult."
Preconstruction coordination between the owner/user group,
the subcontractors, designer and Brasfield & Gorrie was
critical. While labs would be individualized according to
the researcher's needs, it was necessary from a cost and time
standpoint that all of the labs fit into an efficient, cost-effective
design with built-in redundancies.
"We were able to sit down and figure out a system for
a type of lab," Pritchett said. "Most of the labs
are replicas of each other." A redundant design for the
entire facility actually made it easier to accommodate researcher
requests.
"We tried to standardize things as much as possible,"
Bergmann said. With a standard design in place, when individual
requests came along, "We were able to do that on the
fly," he added.
Lab construction actually went smoothly, Pritchett added.
He credited the subcontractors for their design-stage coordination
of the mechanical, electrical, plumbing and other systems.
"Most of the above-ceiling coordination was done by
our subs," he said. "They did an outstanding job.
Very few times did we have to come in and alter something
in the field. Well over 90 percent of it fit perfectly."
Bergmann, who has overseen previous CCRC projects, said he
was impressed with this construction team's ability to accommodate
the owner through this process.
"We had a contractor and an architect that were very
team-oriented," he added. "This is the fourth project
we've done with [O'Neal]. We had never worked with Brasfield
& Gorrie before, but they were very good at listening
to what we had to say."
Everybody Else
The contractor's ability to respond was also important in
dealing with outside interests, such as governmental and citizen
environmental groups, and campus officials, such as the arborist.
Located next to the Oconee River and in the middle of a site
dominated by old-growth trees - including a group of trees
being grown as part of a 20-year-old UGA experiment to replace
the previously extinct American chestnut - the construction
team's activities fell under several watchful eyes.
The sitework stage had its concerns because erosion from
the 10-acre, red-clay site offered plenty of potential for
runoff into the adjacent Oconee River. With the offices of
the state's Environmental Protection Division literally across
the river from the building site, the contractors were being
watched closely and constantly.
"We had major erosion-control concerns," Pritchett
said, adding that the company used several temporary ponds,
lots of riprap material, a couple miles of double-row silt
fence and mulch to minimize the site's impact on the river.
The trees were equally protected.
"We were absolutely forbidden from touching a leaf on
those [experimental American chestnut] trees," which
were contained within a fenced-off tree protection area, Pritchett
said. Numerous other tree types populated the site and also
were protected as much as possible.
"We walked the site with the campus arborist and several
other people who were involved before we cleared any trees,"
Pritchett added. "We made a great attempt to save as
many trees as possible. We tried our best to accommodate the
concerns of all of the groups that were interested in the
environmental impact of the building."
The Results
If there's one thing everyone agrees on, it's the results.
"The project turned out as well, if not better, than
we had hoped for," said Coleman-Silver. "Brasfield
& Gorrie really came through on budget as well as schedule
better than we had hoped."
More important, though, is the perspective of the lead end
user, CCRC Director Darvill.
"The project turned out fantastically well," he
said. "Brasfield & Gorrie did a really fine job,
as did the architect and the project managers. We had a first-class
team from top to bottom. It was a tremendous thing to be a
part of."
The CCRC's most involved person, Bergmann, was also highly
complimentary.
"It was great," he said. "It wasn't flawless,
but we've had 160 to 170 people move into this building within
a month. We're up and working."
Project Team:
Owner: University Architects
for Facilities Planning, University of Georgia, Athens
Developer: University of
Georgia Real Estate Foundation, Athens
General Contractor: Brasfield
& Gorrie, Kennesaw, Ga.
Program Manager: Carter
& Associates, Atlanta
Architect: O'Neal Inc.,
Atlanta
Useful sources:
http://www.ccrc.uga.edu
|