|
Jacksonville Veterans Memorial Arena
Better Jacksonville Plan's
Biggest Project to Date Now a Reality
By Scott Judy
The joint venture of Turner/Perry-McCall/Northside Partnership
has pushed the Better Jacksonville Plan's single biggest project
to date into reality with its completion of the $105 million
Jacksonville Veterans Memorial Arena.
The city-owned, mid-sized arena will seat up to 14,000 for
hockey and arena football games, 15,000 for basketball games
and between 14,000 and 16,000 for concerts. The city dedicated
the new facility on Nov. 19, just two days before an Elton
John concert would bring the new facility to life.
The days leading up to that opening event were frenetic,
though, as project officials with Turner Construction, designer
HOK Sport + Venue + Event of Kansas City, Mo., and dozens
of subcontractors scrambled to pin down final details. Tile
contractors finished up the floors in the concourse area,
glazing contractors buttoned up the exterior windows and wall
contractors applied final finishes.
John Reich, project executive for Turner, said he's proud
that work was completed on Nov. 17, when the team said it
would be. "This arena will have been built in 22 months,"
he added. "It was a very aggressive schedule, so there's
an awful lot of satisfaction."
As work wrapped up, the project's end users were getting
antsy with anticipation.
"Coming from a 40-year-old facility to a facility like
this, this is truly a step above any new arena that I've seen
in the last five or six years," said Robin Timothy, assistant
general manager with Philadelphia-based SMG Inc., the firm
that will market and manage the facility. "I just can't
wait for them to hurry up and get out."
Past Year: Taking Shape
The Turner-led joint venture pushed the project to a topping
out last spring and was able to get it dried in by this past
July.
Getting the structure topped out and the roof on required
a dance between two major subs. Coreslab Structures of Tampa
used several cranes to install the precast concrete seating
risers from the interior of the arena bowl at the same time
that Buckner Steel Erection of Graham, N.C., was erecting
the structural steel frame and roof trusses from outside the
emerging structure.
For safety reasons, these contractors worked from opposite
ends of the project. While they were able to switch ends as
they closed in on each other, eventually both were left with
only work in the middle of the structure. For this reason,
Coreslab Structures had to depart the project for about three
weeks while the steel erector completed its work.
The approximately 16 main trusses connected to a four-girder
box frame that itself connected to four cast-in-place concrete
"supercolumns" designed to support the entire roof
structure. The girders in this box measured approximately
30 ft. deep, Reich said. Additional intermediate struts and
supports further tie those 16 trusses together.
While this phase of the project required significant coordination
for safety purposes, "It went as planned," Reich
said.
In all, the structural steel work required approximately
five months, while the following roof membrane installation
took about three months. Staying on schedule here was critical
to the project's overall timetable.
"The biggest challenge to any arena is getting it dried
in," Reich said. "You have all of these high-end
finishes throughout the arena, in the suites and concourse
areas and the seating areas, and you have to have a dry building
to install that work."
Also critical to getting the building dried in were the efforts
of the mason, Allan Spear Construction Co. of Gainesville,
Fla. With masonry covering nearly the entire exterior of the
roughly 435,000-sq.-ft. structure - and the total number of
brick estimated at 750,000 - Allan Spear's timeliness was
going to impact the work of numerous other subs and the project's
overall progress.
"The exterior masonry started pretty much as soon as
we got the structure topped out," Reich said. "We
were still pouring the upper concourse when the mason came
in and started putting in his masonry backup. He was basically
following the structure up."
Coordination with the steel erector was an issue as well.
"That was the biggest challenge - keeping the mason
from having to work under the steel contractor," Reich
added.
With the steel erector moving around the project, the mason
needed to be more nimble than usual. For this reason, Allan
Spear invested in a self-climbing scaffold system that it
used to more quickly set up and work in open areas. With several
of these units located around the structure's perimeter, the
mason could move to another area on short notice.
"If the structural steel needed to work over him, he
could pull off and go to another scaffolding and not have
to build (scaffolding)," Reich said.
Allan Spear Construction also initiated a change order that
increased its efficiency. Instead of using the standard-sized
brick included in the original bid package, the mason suggested
moving to a larger brick to reduce labor costs and speed the
project.
Reich said the masonry job was tough.
"This isn't a real simple building," he said. "It's
not just flat, straight walls. There's a radius along the
whole north wall. You have so many inside and outside corners.
They did a good job for us."
Part of a Bigger Design
While the new Veterans Memorial Arena may stand apart, it
doesn't stand alone. As part of the city's "Sports Complex"
district - which includes Alltel Stadium and the new minor-league
Baseball Grounds of Jacksonville - the new facility was designed
to be part of a greater whole.
HOK Sport + Venue + Event, the designer for the arena, was
also involved with the design of the recently completed Baseball
Grounds as well as the transformation of Alltel Stadium several
years ago.
Bradd Crowley, project manager for HOK, said the first step
was to position the arena and ballpark projects within the
proposed district.
"We proposed that the arena rest exactly where it's
sitting today - directly across from the ballpark, on axis
with Alltel," he said. "We were excited about the
energy the ballpark and arena would have playing off of each
other."
Crowley said the exterior designs of the arena and ballpark
across the street took their cues from the existing architecture,
most notably a small brick church facing the arena's entrance.
"The (church has) this red brick, and some precast that
accents the red brick," Crowley said. "A lot of
the shapes were pulled from the glass and from that (church)
structure. That was the birth of the brick material on both
the ballpark and the arena."
Inside the arena, the "energy" can be felt through
the extensive use of glass curtain walls that provide arresting
views of the Jacksonville skyline and neighboring ballpark.
Large exterior balconies are actually functional, enabling
patrons to also go outside during their visits.
"We tried to pull the outside into the seating bowl,
and actually all the way into the bowl, where we've opened
up the concourses in very wide areas that can really get some
outside light," Crowley said.
Another incorporation of the surrounding community can be
found in the inclusion of a Hall of Fame area within the arena's
entrance lobby. This area will serve as a Florida Sports Hall
of Fame, Florida/Georgia Hall of Fame and Jacksonville Hall
of Fame.
"We were always looking for something that would bring
a little excitement to that lobby," Crowley said. "Prior
to that Hall of Fame coming about, it was a blank wall. Nothing
really made sense until that came along. And really all we
had to do was take a little bit of storage space and incorporate
it in there.
"We're real happy with that late addition to the project
(and) very excited about the lobby," he continued. "It
kind of explodes upwards with crisscrossing escalators and
elevators."
Multifunction
Though the arena doesn't have a major-league sports tenant,
its amenities are designed toward that level, with 28 suites,
including four party suites and one large "party deck"
that seats about 120.
Turner's Reich said only a few suites had not been sold yet.
"It's a big hit here in town," he said. "They
could bring an NBA team in here. They'd have to make some
modifications to some of the parking arrangements. But you
could take this (facility) and put it in any major city and
it would be comparable, and maybe even better, than a lot
of other arenas."
Crowley said he believes the amenities in the new arena are
"maybe a little more extensive and a little more upscale
than some mid-sized arenas."
Without a major-league sports tenant, the arena's main function
will be to serve multiple purposes, most notably entertainment
events.
"This facility is really leaning a little more to the
entertainment end rather than the sports end, though it will
handle the sports magnificently," Crowley said. "The
sightlines are great for basketball and hockey and, of course,
concerts."
The level of amenities on this project has been a function
of the budget. As a result of excellent subcontractor pricing
and the normal value-engineering process, the Turner-led team
and the city were actually able to add some amenities, such
as premium retractable seats that can be placed on the arena
floor for concerts. These seats are identical to the rest
of the facility's permanent seats.
Dollar for dollar, Reich said the new facility stands up
well. "For the cost, and what they're getting for it,
I would put this one up against any major city's (arena),"
he said.
"We're really excited about the finished product,"
Crowley added, just days before the opening. "We can't
wait for the first event, and 15,000 - 16,000 people coming
in there and enjoying themselves."
Project Team:
Owner:
City of Jacksonville
Construction Manager: Turner/Perry-McCall/Northside
Partnership, Jacksonville
Architect: HOK Sport +
Venue + Event of Kansas City, Mo.
Masonry Contractor: Allan
Spear Construction Co., Gainesville, Fla.
|