|
Aventura Hospital and Medical Center
Centex Rodgers Builds a High-Rise
Tower for South Florida Hospital
by Debra Wood
Aventura Hospital and Medical Center plans to start moving
into its new $130 million facility by late spring. The hospital
features a structural steel frame structure with precast concrete
exterior skin.
"We needed to bring our facility, from a technology
and customer-service standpoint, into the 21st Century,"
said Davide M. Carbone, Aventura Hospital's chief executive
officer. "The replacement of a majority of our patient
rooms was one of our unique challenges."
The nine-story, 146-ft. tower includes 245 private rooms,
a 26-bed emergency department, two intensive-care units and
10 new operating rooms. In addition to the nine functioning
floors, two others are being used as interstitial space and
mainly house mechanical equipment.
"This project is atypical in that it is a high-rise,
and no one builds a high-rise hospital in the state of Florida,"
said Tom Koulouris, construction manager for project owner
HCA. "Very tight site restraints are what drove that."
Nashville-based Centex Rodgers, with offices in Palm Beach
Gardens, Fla., received the contract and began sitework on
the multiphased project in spring 2001. Construction costs
on the structure are approximately $90 million, which includes
a parking garage and renovation to the existing building.
The contractor is adding a new EIFS exterior and hurricane
wind-resistant windows to the old facility.
Craig Eckert serves as project manager for Centex Rodgers.
Before Centex Rodgers could start constructing the tower,
it had to build a six-story, 815-space parking garage, which
opened in November 2001; tear down an existing garage attached
to the functioning hospital; and relocate underground utility
lines.
To save more space, Aventura located the central energy plant
on adjacent property across the street from the hospital.
Crews trenched across two city streets and skirted a Miami-Dade
County sewage lift station to bring supply-and-return chilled-water
pipes and an emergency electrical duct bank to the new facility.
The structure evolves
Aventura began planning the addition in 1995 and received
corporate funding for a three-story addition in 1999. Architects
Gresham Smith and Partners of Tampa designed that structure
with the potential for 15 stories.
By 2001, Aventura had the money to add the patient-room floors.
Future plans still include three more floors and additional
elevators.
"The biggest limitation was whatever we built was an
expansion, not a replacement facility, and so it had to work
with the existing facility," Carbone said. "The
existing facility was never designed for acute care."
The Teamsters union built the structure in 1974 as a rehabilitation
hospital but never moved in. It later opened as a community
hospital. The first three floors are only 12 ft. from slab
to slab. And the remaining floors have about 10-ft., 6 in.
of clearance.
"Typically in health-care projects, you need a lot more
room than that because of the amount of utilities that go
above the ceiling," said Matt Harrell, architect for
the project. "We have a pretty significant HVAC system
that requires special filtration and air volume, with return
and supply."
Harrell said the new floors will be double high. The new
second level aligns with the existing third floor and the
new third, with the existing fifth floor.
Corridors will connect the two buildings. A domed rotunda
with wood accents and warm colors will give the new entry
space the appearance of a hospitality facility rather than
a medical center.
A main central nurse station, with decentralized support
spaces and bedside charting, allows the 42-room patient floors
to function as a single unit. Charting and workstations are
interspersed near patient rooms. Some flex rooms have been
designed to function as intensive-care beds if needed. Upper-floor
windows offer striking views of the ocean and surrounding
community.
Work commences
When Centex began working on the tower, it leased nearby
property to assist with dewatering. Excavations for pile caps
were 12 to 14 ft. below grade. It pumped water continuously
for three months into a temporary lake, and the water eventually
percolated back into the ground.
After demolishing the existing garage, Centex unexpectedly
found concrete piles, which had to be extracted before starting
to drive new piles to support the structure. As-built drawings
did not exist.
Crews drilled nearly 700 16-in., 40-ft. long auger-cast piles
for the foundation. To monitor noise and vibrations, Centex
Rodgers sent personnel into the existing hospital to assess
any problems. It coordinated closely with hospital operations
personnel and stopped vibratory compacting a couple of times
when certain surgeries were taking place.
The new building rose close to the existing structure, and
patients could watch the progress.
"We were hanging precast panels that weighed 42,000
lbs. right next to the existing building, within 2 in.,"
Eckert said. "We were nervous but made sure we had our
measures in place."
The project has had 35 subcontractors and about 300 workers.
"We tried to emphasize using local participation as
much as possible," Eckert said. "The majority of
subcontractors are locally based."
Koulouris said the "showcase" project has progressed
smoothly once permitting was obtained. All phases, including
renovations to the existing structure, should be complete
by late fall.
Useful Sources:
- http://www.centex-construction.com/ourcompanies/rodgers.asp
- www.aventurahospital.com
|