|
Jacksonville Construction Report
Momentum building as 2005 Super
Bowl nears
by Debra Wood
Jacksonville contractors are enjoying a healthy increase
in new volume, as private and public projects move forward,
some in anticipation of next year's Super Bowl.
"We're still in a very good position with the Super
Bowl coming here in 2005," said Stevan A. Hall, executive
vice president of AGC of Greater Florida. "That has already
created some construction opportunities and will continue
to create opportunities."
The Haskell Co. of Jacksonville is on target for completing
a series of upgrades at the NFL Jacksonville Jaguars' Alltel
Stadium in time for the big event. It also will begin work
by the end of 2003 on a design-build-operate project for two
parking garages, one at the sports complex and another at
the nearby sports and entertainment arena. Both parking facilities
must be complete before game day.
AMEC Civil of Fort Myers still hopes to complete reconstruction
of the $100 million Interstate 295/I-95 interchange for the
Florida Department of Transportation by Jan. 15, 2005. If
it succeeds, the company will earn a $5 million bonus.
But the complex job generated noise complaints from nearby
residents, hampering nighttime progress. Legal action is pending.
The multidimensional interchange was half complete in October.
"We're skeptical but hopeful," said Mike Goldman,
FDOT spokesperson. "We're still giving them the window
of opportunity, and we'll see. They're out there, but it's
an extremely difficult job."
The Big Picture
Not all Jacksonville projects tie into the football hoopla.
New industrial, condominium projects and growth in surrounding
counties have spawned opportunities.
"The construction market has been fairly good,"
said Dan Haskell, president of Associated Builders and Contractors,
Florida First Coast Chapter in Jacksonville. "There's
a general upbeat attitude about everything. Most contractors
are feeling there is going to be plenty of work out there."
That supports a report from the Dodge Analytics unit of McGraw-Hill
Construction. Nonresidential August contracts in the four-county
Jacksonville metropolitan area increased by 47 percent and
year-to-date by 21 percent.
"The Jacksonville market has always been a little bit
recession proof," said Gordon Steadman, director of development
for Elkins Constructors of Jacksonville. "It does not
fluctuate as much as some other cities."
Government Upgrades
All major vertical Better Jacksonville Plan projects have
been let, Hall said. "They will still be constructing
over the next two, two-and-a-half years," he added. "That
will keep people busy, but those dollars are spent."
A joint venture of Auchter-Elkins-Lodestar-Paris of Jacksonville
serves as construction manager for the BJP's five-story main
library. The project was about 25 percent complete in October
and should finish in the first quarter of 2005.
Sitework has begun on the Duval County Courthouse, while
budget negotiations continue for building the $211 million
project. The city selected for construction management a joint
venture partnership that includes Skanska USA Building, SL
Construction & Remodeling, Hernandez Enterprises and QC
Management, all with offices in Jacksonville.
Perry-McCall Construction Co. of Jacksonville has completed
about 60 percent of the Cecil Equestrian and Recreation Complex,
a $29 million BJP project at Cecil Field, a decommissioned
Naval facility.
Numerous smaller BJP projects, including park, roadway and
regional library improvements also are under way.
Segment 1 of the Jacksonville Transportation Authority's
Wonderwood Connector has experienced some utility delays,
but the 2-mi. project should still finish during the third
quarter of 2004. Martin K. Eby Construction Co. of Maitland
was scheduled to complete Segment 2 by the end of 2003. And
JTA plans to pull permits for Segment 3 by the end of 2004
and start construction in 2005.
FDOT expects Superior Construction Co. of Jacksonville to
finish this spring a $15.8 million, low-level bridge on Heckscher
Drive at the Fort George Inlet.
Jacksonville International Airport began a $25.5 million,
40,000-sq.-ft. terminal expansion in July to consolidate passenger
checkpoints. Completion is set for October.
Turner Construction Co. of Orlando will provide construction
management services on the University of North Florida's 115,000-sq.-ft.
library addition.
Perry-McCall has begun construction on Florida's first proton
beam cancer treatment facility at Shands Jacksonville.
And JEA has been weighing two bids for redevelopment of its
40-acre Southside Generating Station site to a mixed-use retail/residential
complex. The St. Joe Co. and the Haskell Co. were the two
short-listed firms that had submitted proposals for the project.
Private Starts
The combination of baby boomers looking for residences with
less upkeep, a lagging stock market and cheap money have resulted
in "condo work going through the roof," said Bob
Renaud, manager of public affairs for the Haskell Co.
The company is under contract for a two-tower, 110-unit complex
south of downtown.
Brasfield & Gorrie of Maitland has received a contract
to build the first of three nine-story condominium buildings
at Marina San Pablo. It also is building 100 luxury condos
at The Shipyards, a mixed-use redevelopment project.
And Deerwood Development, of Coconut Grove, Fla., is building
a 440-unit Tuscan-style complex called Il Villagio in Deerwood
Park North.
Haskell also has broken ground on Baptist Medical Center
South, a $60 million, 92-bed satellite facility in Flagler
Center in southeastern Duval County. It also is building a
structural-steel clinical-services building for Baptist Health.
Turner was selected to manage construction of the CitiGroup
Office Complex. And Hardin Construction Co. of Atlanta will
manage sitework, hardscape and building shells at St. John's
Town Center, a big-box and lifestyle center southeast of Jacksonville.
Ring Power Corp. of Jacksonville, a Caterpillar dealer, selected
Elkins to build its headquarters facility at the World Commerce
Center in St. Johns County. The structure will include industrial
space and a four-story, class-A office building. The 13-month
project will finish in fall 2004.
Brazilian aircraft manufacturer Embraer announced plans to
build a 71,000-sq.-ft. aircraft assembly facility at Cecil
Commerce Center. It has a contract pending with military aerospace
contractor Lockheed Martin Corp. of Bethesda, Md.
Industry leaders seem more upbeat this year. Pricing remains
aggressive, but with Jacksonville and the surrounding counties
growing, there will likely be plenty of work.
"Overall, the national economy is picking up,"
AGC's Hall said. "I think Florida, through this economic
downturn, has remained relatively strong. Contractors seem
to be pretty comfortable with what they're doing and have
some good things lining up."
Useful Sources:
More information about construction activity in the greater
Jacksonville area can be found at the following:
|