Features
 Current Features
 Past Features





Features - November 2003

Design-Building I-77

Rea Construction hoping to close out NCDOT's first design-build road job

As other states have done, the North Carolina Department of Transportation recently adopted design-build as a viable project-delivery method. Charlotte-based Rea Construction turned NCDOT's first design-build roadway project into a nationally award-winning effort - but clouds still linger over the contract's ultimate completion.

by Scott Judy

Even though Charlotte-based Rea Construction jumped out to a five-month lead, and has since won national awards for its efforts, the firm is now struggling to finish its $84 million Interstate 77 contract in Charlotte on time.

Whether the J.A. Jones subsidiary ultimately proves successful in its goal remains a question mark, but Rea's achievements related to safety, project innovation and community interaction are likely to endure.

"They've done an outstanding job," said Rick Baucom, resident engineer with NCDOT.

advertisement

That's notable, as this contract represents the North Carolina Department of Transportation's first-ever design-build roadway project. The contractor's efforts also have garnered national awards from the National Asphalt Paving Association and the American Road and Transportation Builders Association for safety and public relations.

Rea won the contract through a qualified-selection basis with a bid of roughly $71 million. Through a supplemental agreement added to the project later, the total cost of the contract increased to about $84 million. The main scope of the contract was to widen roughly 8.1 mi. of I-77 from four to eight lanes, within the existing right-of-way.

HDR Engineering is the project's engineer, with Ralph Whitehead Associates, Charlotte, assisting. In its original proposal, the Rea-HDR team committed to a schedule that would complete the project 125 days ahead of the DOT's November 2004 completion date. Even with the added scope, the new completion date of early October is still ahead of that.

Rea started work in December 2001 - not the optimal time to begin construction.

"Traditionally, companies would rebuild the outside shoulder, [then] shift traffic to the outside and then start working on the inside," said Kipp Cheek, project manager for Rea. "We jockeyed with some of the alignments that allowed us to start work in the median immediately, and that probably saved us five or six months because the project started in wintertime when you couldn't do a whole lot of paving."

This first phase of the project would include grade preparation for the length of the project, with asphalt paving work beginning in April. The existing road had been originally built as concrete and later overlaid with asphalt. Under Rea's contract, the new lanes would be built with asphalt, and the existing mainline milled and replaced with new asphalt of roughly 6 in.

Getting into the median was a trick. Rea's solution to the median-access problem would win it NAPA's first-ever "Workzone Safety Innovations Award" and ARTBA's "2002 National Work Zone Safety Award."

Working with design subconsultant Ralph Whitehead Associates and subcontractor F.T. Williams, the team built a 28-ft. earthen ramp in the median up to the W.T. Harris Boulevard bridge over I-77. The ramp presented its own unique design and construction challenges.

"The shoring had to not only support the ramp, but also protect the proposed Harris Boulevard bridge footings to be constructed at the base of the sheet piling," Cheek said. "This meant the sidewall height of the ramp would be over 20 ft. Since the front wall of the ramp would be directly against the existing bridge, deflection of this sheeting could not exceed .5 in., with only 1 in. of clearance between the ramp and existing bridge."

The contractors removed the bridge's outside rail and repainted the bridge lane stripes to make narrower lanes and to provide for a "truck-only" lane, enhancing the safety of the truckers as well as the motorists traveling on I-77 and Harris Boulevard. The state highway patrol cited this innovation for the low number of accidents on the interstate within the project limits.

By using the ramp, Cheek said, "We never had to put a dump truck on the interstate. That was important because it allowed us to do the work during the day, and it helped us accelerate the project."

Without such an approved plan, NCDOT was going to restrict truck hauling to night hours only. The project required the truckers to make an estimated 250 trips per day from the nearby asphalt plant to the jobsite.

Supplemental Agreement

After the median work, Rea and its team of subcontractors began reconstructing the existing lanes and all construction on outside existing lanes, such as the new shoulders. Rea handled the asphalt-paving work itself.

Subcontractors Delta Contracting and American Milling handled various portions of the milling, which involved taking 2.5 in. off the existing asphalt mainline for the entire length of the project.

A major change in the project occurred at the I-77/Interstate 85 interchange. Going in, the intent had been that all lanes would be general-purpose. Later, NCDOT opted to have both inside north- and southbound lanes serve as high-occupancy vehicle lanes. As the project progressed, the team discovered there was insufficient room to get all of these lanes under the I-85 overpass.

As a result, NCDOT and the project team agreed to separate out the southbound I-77 HOV lane into an elevated structure - aligned over the northbound HOV lane - that would pass over I-85.

"When you're running south and you get to the I-85 interchange, there's a two-lane ramp that runs into the southbound lane," Cheek said. "With that and the bridges, there wasn't enough room. So for that fourth lane we built its own road up and over the interchange and back down the other side."

Design-Build Different

This project was a first for Rea Construction and NCDOT.

"Going into this, there was really no script on how it was [to be] done," Cheek said. "So we were kind of pioneers on building a road using the design-build method."

To accelerate the project, the team divided it up into small segments, so construction could proceed as quickly as design work was completed. This helped the contractor get started as soon as possible and eased the burden on the NCDOT staff, which was facing a turnaround time for contractor submittals that was limited to 10 days, instead of the usual 30 to 45.

"Splitting the job into segments allowed DOT to not be overwhelmed," Cheek said. "We tried to make our submittals small."

For NCDOT, this was a significant change. "A 10-day turnaround on submittals meant a really big change for our design people in Raleigh," engineer Baucom said. He added that for the most part, though the department was able to meet the deadline.

"The department is generally happy with design-build," Baucom said. "To get that design-build done that way, the department had to relinquish the control it has on the design."

This cultural change has been more positive for the contractor.

"I have fallen in love with it," Cheek said of the design-build process. "It takes a lot more energy than traditional projects. It takes a lot more communication than traditional projects. And obviously it takes more resources. But it's exciting because I know we're giving the taxpayers an efficiently built road.

"As a contractor, we have the opportunity to build the road the way we want to. We're kind of controlling our own destiny for the first time in our lives, and that's exciting."

A couple of items out of Cheek's control, however, are Mother Nature and the financial status of Rea's parent company, J.A. Jones. While area rains eroded the contractor's five-month lead, J.A. Jones' well-documented financial struggles have darkened the Rea team's prospects going into the project's final stages.

"The rain has killed us," Cheek said. "And our company has had some financial struggles that are hindering us. So we're being overly challenged on finishing the project, especially since we had such a good start on it. We still have hopes of finishing on time."

Interstate 77 Design-Build Team

Owner: North Carolina Department of Transportation
General Contractor: Rea Construction Co., Charlotte
Engineer: HDR Engineering, Charlotte
Engineering Consultant: Ralph Whitehead Associates, Charlotte
Construction Inspection: Mulkey Engineering, Raleigh, N.C.
Milling Contractor: Delta Contracting
Milling Contractor: American Milling

Useful Sources:

For more information about this project, readers may visit the following sources:

 Click here for past Features >>



 


Network Sponsors

© 2009 The McGraw-Hill Companies, Inc.
All Rights Reserved