|
Purrysburg Water Treatment Plant
Owner and Contractor Expedited $29 Million Project to Meet Needs of New Power Plant
by Debra Wood
Contractors, engineers and an owner motivated to deliver
water on time to a new electrical generating plant have worked
together to bring in ahead of schedule the fast-tracked Purrysburg
Water Treatment Plant project in South Carolina.
“We took a strong teamwork approach,” said Jennifer Barrington,
special projects manager for owner Beaufort-Jasper Water &
Sewer Authority of South Carolina. “Keeping the communication
open has been a major contributor to how well everything is
going.”
Construction on the $29 million project began in April 2002,
and the Pizzagalli Construction Co. of South Burlington, Vt.,
is on target to finish the project by the contract date of
April 2004. The project is in Beaufort County, which Barrington
said is the state’s fastest-growing county.
BJWSA initially planned a design-build project, which developed
into an expedited fast-track contract when South Carolina
Electric & Gas decided to build a generating plant on adjacent
property.
“The water authority in the past has generally done a straight
design-bid-build,” Barrington said. “We took a little more
innovative approach on this one and we’ve been able to shorten
the schedule a good bit by doing so.”
Jordan Jones & Goulding of Atlanta continued working on the
design during the permitting and contractor selection process.
BJWSA representatives visited projects under way or completed
by the top three contenders before choosing Pizzagalli.
Once on board, the contractor provided value engineering,
which saved the utility money on pipe materials, and made
recommendations about constructability.
Electrical subcontractor Cogburn Bros. of Jacksonville, Fla.,
also suggested changes that favorably impacted the budget.
Construction began with 30 percent of the design complete.
BJWSA partnered with SCE&G to supply drinking, raw and reverse-osmosis
water for the nearby generating plant. The reverse osmosis-water
is stripped of minerals to decrease buildup inside the power
equipment.
The electrical and water plant projects are on similar completion
schedules, and BJWSA was required by the power company to
meet multiple intermediary deadlines. “Schedule became the
primary driving force,” Barrington said.
Site work subcontractor Malphrus Construction of Hilton Head,
S.C., built a 60-acre raw-water reservoir through months of
rainy weather, losing only two days.
Keeping the water flowing to customers was vital and required
some coordination. An 18-mi.-long open canal feeds water to
BJWSA’s other plant. Crews had to run pipes to feed the new
plant under one side of the existing plant’s canal to the
other.
“We had to cross the canal with a 36-in. and 54-in. piping,
and we had a four-day window to shut the canal down, open,
excavate and install the piping across the canal,” said Andy
Potts, project manager for Pizzagalli.
The project also includes construction of a reservoir pump
station; a flocculation basin, where the cleaning process
begins; a sedimentation basin; a filtration building; a chemical
supply building; a 4-million-gallon finished water storage
tank; and an administration and control building.
The new plant will produce 10 million gallons of drinking
water per day and is upgradeable to 30 gallons per day.
The poured-in-place concrete project consumed 10,000 cu.
yds. of concrete, and 1,000 tons of rebar were placed.
About 70 workers are onsite, working primarily four 10-hour
days.
Barrington said, given the same demands, the water utility
would consider using the fast-track approach on future projects.
“It has worked so successfully here,” she added. “I am most
proud of what we have accomplished so far. We’ve accomplished
it through a hard-working contractor, hard-working engineers
and the ability to effectively communicate.”
Purrysburg Water Treatment Plant Project
Team:
Owner: Beaufort-Jasper Water
& Sewer Authority, Beaufort, S.C.
General Contractor: Pizzagalli
Construction Co., South Burlington, Vt.
Engineer: Jordan Jones and
Goulding, Atlanta
Electrical Contractor: Cogburn
Bros., Jacksonville, Fla.
Site-Work Contractor: Malphrus
Construction, Hilton Head, S.C.
Useful Sources:
For more information about this project’s contractor, please
visit: www.pizzagalli.com
|